Fifth Circuit Disallows Equitable Defenses to Limitations Under Texas Performance Bond Statute

Hartford Fire Ins. Co. v. City of Mont Belvieu, Texas, No. 09-40586 (5th Cir. July 13, 2010)

By:  David Coale & Billie Ann Maxwell, K&L Gates, Dallas

This case shows why it is important for governmental entities, their contractors, and performance bond providers to be aware of statements among the parties for limitations purposes, and the application of equitable defenses, in the context of the one-year limitations period under Texas Government Code § 2253.078(a).  The lessons of this case apply fully to similar statutes in other jurisdictions.

Continue Reading...
Tags:

California Court of Appeal Clarifies Definition of Retention Payments Under Civil Code ยง 3260

Yassin v. Solis, 184 Cal. App. 4th 524 (Cal. Ct. App. 2010)

By: Carlo L. Rodes and Brett D. Bissett, K&L Gates, Los Angeles

In this case, the court of appeal set forth a definition for retention that applies whenever a contractor seeks an award of penalties for improperly withheld retention under a California prompt payment statute.

The plaintiff-contractor, Diaa Yassin was hired by the defendants-owners, (collectively “Solises”), to improve the Solises’ home.  Under the contract, Yassin was to receive a series of payments throughout various stages of construction and the last payment was to be made upon completion of the work and before occupancy.  Yassin ultimately sued the Solises for money allegedly owed under the contract.  Although the court addressed other matters, a principal issue was the status of the final two payments of $15,000 and whether those amounts qualified as retention payments under California Civil Code § 3260.  Under section 3260, if an owner fails to make retention payments within the time prescribed by that section, a contractor may recover a penalty in the amount of 2 percent per month on the improperly withheld amount plus attorney fees.

Continue Reading...

Lien Held Invalid for Failure to Comply with Statutory Attestation Requirement

Williams v. Athletic Field, Inc., No. 33607-3-II (Wash. Ct. App. Apr. 7, 2010)

By: Jesse O. Franklin IV and Bradley D. Bowen, K&L Gates, Seattle

This case demonstrates the importance for claimants to substantially comply with Washington’s lien statutes.  The issue in Williams was whether a lien is invalid if a lien filing service employee signs the lien’s attestation clause, rather than a claimant or the claimant’s attorney.  The Court in Williams held that an agent of a claimant can sign a lien’s attestation clause under RCW 60.04.091, addressing the recording of liens, including an employee of a lien filing service.  However, the Court went on to hold that when the claimant’s agent is also a corporation, like a lien filing service, the agent must comply with the corporate acknowledgement requirements under Washington law.  Moreover, the Williams case stands for the more general proposition that a lien claimant in Washington must clearly demonstrate that all statutory lien claim requirements have been met because courts strictly construe the lien statutes.

Continue Reading...

Texas Supreme Court Finds Jurisdiction over Foreign Manufacturer

Spir Star AG v. Kumich, No. 07-0340 (Tex. Mar. 12, 2010)

By: David Coale & Matthew Sikes, K&L Gates, Dallas

The recent Texas Supreme Court case of Spir Star AG v. Kumich affirmed jurisdiction over a foreign company that had deliberately structured its Texas business to be conducted through a separate intermediary.  No. 07-0340 (Tex. March 12, 2010).  This case illustrates an aspect of personal jurisdiction over foreign entities that can be critical to disputes about projects involving overseas consultants or specialty contractors.

Continue Reading...
Tags:

Fifth Circuit Upholds Use of Contractual Interim Orders and Progress Payments to Preclude Contractors from Obtaining Further Payment for Extra Work

Addicks Servs., Inc. v. GGP-Bridgeland, LP, 2010 WL 4250054 (5th Cir. Feb. 8, 2010)

This case shows the effectiveness that explicit waivers and progress payments can have on precluding contractors from obtaining further pay for alleged extra work.  A contractor sought damages for extra work and delay costs incurred in performing excavation and grading work for a developer.  The Fifth Circuit, applying Texas law, granted summary judgment in favor of a developer because the interim waivers and accompanying progress payments unambiguously released any outstanding claims for payment of extra work performed before the date of each interim waiver. 

Continue Reading...
Tags:

Washington Supreme Court Holds the Statute of Limitations Does Not Apply to Safeco Field Construction

Wash. State Baseball Stadium Pub. Facilities Dist. v. Huber Hunt & Nichols-Kiewit Constr. Co., 202 P.3d 924 (Wash. 2009)

The Washington Supreme Court recently issued a decision in Wash. State Baseball Stadium Pub. Facilities Dist. v. Huber Hunt & Nichols-Kiewit Constr. Co. that may have far-reaching impact on other public construction projects.  In that case, the Court unanimously held the statute of limitations does not apply to claims regarding the construction of Safeco Field brought by the owner, the Washington State Baseball Stadium Public Facilities District (“PFD”), because the construction was for the common good of the state.

At issue were construction defect claims filed by the PFD against its general contractor. The PFD alleged the general contractor failed to follow the intumescent fire protection specification for structural steel members, causing a catastrophic failure of the fire protection. The PFD discovered the defect in 2005, and filed the lawsuit in 2006. This was more than seven years after substantial completion of Safeco Field; the applicable statute of limitations for contract claims is six years. RCW 4.16.040.

The Supreme Court overturned a summary judgment dismissal of the PFD’s claims granted by the trial court, and held that the statute of limitations does not apply. The Court relied on statutory language providing that limitation periods do not apply “to actions brought in the name or for the benefit of the state.” RCW 4.16.160. The majority of the Court’s opinion grapples with the question of whether the PFD brought the construction defect action “for the benefit of the state.”

Continue Reading...

Court Declines to Find Construction Company "Statutory Employer" of Injured Worker, Denies Construction Company's Motion for Summary Judgment

Baugh v. Gale Lim Holdings, Inc., 2009 WL 33149 (D. Idaho Jan 5, 2009)

In this case, Gale Lim Construction contracted with the State of Idaho to repair portions of the Tin Cup Highway.  Lim contacted Silver Star Communications before excavating, as required, and Silver Star then sent its employee, John Baugh, to the jobsite to mark its fiber optic cable.  Baugh was injured and brought a tort action against Lim.

Lim filed a motion for summary judgment claiming that worker's compensation law made it a "statutory employer" of Baugh and therefore immune from tort claims.  Baugh defended the motion by arguing that immunity was not applicable in this case where there was no contract between Lim and Silver Star.  Holding that a question of fact remained as to the existence of a contract, the court denied the motion.

Continue Reading...
Tags:

Court Determines That A Builder May Seek Equitable Indemnity Against A Manufacturer Under California's Right to Repair Act

Greystone Homes, Inc. v. Midtec, Inc. 168 Cal.App.4th 1194 (Cal. Ct. App. 2008)

California’s Right to Repair Act (Civil Code section 895 et. seq. or the “Act”) establishes a set of standards for residential construction and provides tort liability for failing to meet those standards. The Act was enacted in response to the California Supreme Court’s decision in Aas v. Superior Court, 24 Cal.4th 627, 636 (2000), which held that “[i]n actions for negligence, a manufacturer’s liability is limited to damages for physical injuries; no recovery is allowed for economic loss alone.” In other words, under Aas, the “economic loss rule” precluded recovery for damages such as “the difference between price paid and value received, and deviations from standards of quality that have not resulted in property damage or personal injury.” The Act, however, abrogated the Aas decision by permitting a homeowner that established a violation of the Act to recover economic losses from a builder, among others, without having to show that violation caused property damage or personal injury.

In the recent case of Greystone Homes, Inc. v. Midtec, Inc., the California Court of Appeal ruled on the following two issues that had not been previously addressed under the Act: (1) whether a builder may recover for economic loss caused by a product manufacturer’s violation of the Act through a claim for equitable indemnity against that manufacturer; and (2) whether that builder may bring a direct action for negligence against the manufacturer to recover its economic losses. As discussed below, the court concluded that a builder may bring an action for equitable indemnity to recover economic loss as a result of a manufacturer’s violation of the Act, but a direct claim for negligence is not permitted.

Continue Reading...

Idaho's High Court Analyzes 15 Factors for Determining Whether a Worker is an Independent Contractor or an Employee

Excell Constr., Inc., v. Idaho Dep’t of Commerce and Labor, 145 Idaho 783, 186 P.3d 639 (2008)

This appeal arises out of an Idaho Industrial Commission finding that certain sheetrock workers hired by Excell Construction were employees rather than independent contractors.  At issue was whether Excell would be required to pay $6,353 in unemployment insurance taxes and penalties.  On appeal, the Idaho Supreme Court held the workers were independent contractors and reversed the Commission’s finding.

Continue Reading...
Tags:

Contractual Limitation of Liability in Engineer / Survey Contract Upheld

Blaylock Grading Co., LLP v. Smith, 658 S.E.2d 680 (N.C. Ct. App. 2008)

In this case, a grading contractor sued a surveyor (who was also an engineer) for breach of contract and negligence regarding mistakes in surveying work which resulted in the contractor having to incur costs to import fill to raise the elevation of the site.  The contract between the contractor and surveyor contained a provision limiting the surveyor’s liability to $50,000.  The surveyor unsuccessfully moved for partial summary judgment based on the limit of liability.  Following a jury verdict against the surveyor for $574,714, the surveyor moved for judgment notwithstanding the verdict, which the trial court denied, ruling that the limit of liability was void as against public policy.  The North Carolina Court of Appeals reversed the trial court, holding that the limitation of liability was valid and enforceable.

Continue Reading...

Foreign Contractor's Failure to Register with Secretary of State Does Not Void Contract or Arbitration Clause

City of Westfield v. Harris & Assocs. Painting, Inc., 567 F. Supp. 2d 252 (D. Mass. 2008)

In this case, the Federal District Court for the District of Massachusetts allowed a contractor’s motion to compel arbitration and remanded the case to arbitration despite the fact that the contractor failed to register as a foreign corporation with the Massachusetts Secretary of State as required by M.G.L. c. 30, § 39L.

Continue Reading...

Inclusion of Disallowed Items in Lien Not Always Bad Faith

Politano v. GPA Constr. Group, 2008 WL 515661 (Fla. Dist. Ct. App. Dec. 10, 2008)

In Politano, an owner moved to discharge a contractor's lien for willful exaggeration based on the contractor's inclusion of overhead and profit.  The Third DCA affirmed the trial court's decision to reduce the amount of the lien accordingly, but not discharge the lien based on the finding that the disallowed items included in the lien were a result of mistake not willful exaggeration.  It rejected the owner's argument that a lien is willfully exaggerated if it includes non-lienable items without regard to ignorance or good faith, or that a court's reduction of a lien amount necessarily means the original lien amount was fraudulent.
 

Court Rules Contractor's Failure to File Action or Counterclaim to Enforce Lien within 20 days in Compliance with the Statute Requires Discharge of the Lien

Brookshire v. GP Constr. of Palm Beach, Inc., 99 So.2d 179 (Fla. Dist. Ct. App. 2008)

In Brookshire, an owner filed a complaint to discharge a contractor’s lien and the clerk issued an order to show cause under Florida Statute Sec. 713.21(4).  Accordingly, the contractor had 20 days to show cause as to why his lien should not be enforced by action or vacated and cancelled of record.  Failure to do so would result in cancellation of the contractor’s lien.  The contractor filed a motion to compel arbitration and set it for hearing within the 20 day period, but did not respond to the show cause order.  The contractor argued that the motion to compel satisfied Section 713.21.  The appellate disagreed and directed the trial court to discharge the lien.

The contractor had argued that the motion to compel arbitration satisfied Section 713.21 because the dispute would ultimately be arbitrated and the contractor wanted to avoid any issue as to whether he was waiving arbitration.  The court held that Section 713.21 does not allow for exceptions, such as extensions of time, nor does it leave the court with any discretion to excuse a failure to comply.  The court also noted that any concern regarding waiving arbitration could have been satisfied by contemporaneously filing a motion to arbitrate those issues that were allegedly subject to arbitration.

Court Holds Action on Performance Bond Accrues Upon Contractor's Acceptance of Subcontractor's Work and Payment for that Work in Full

BDI Constr. Co. v. Hartford Fire Ins. Co., 2008 WL 4568075 (Fla. Dist. Ct. App. Oct. 15, 2008)

In BDI Construction Co., a subcontractor filed a third party action on a sub-subcontractor’s performance bond.  The surety moved for summary judgment claiming that the agreed five-year statute of limitations under Florida Statute Section 95.11(2)(b) began to run when the subcontractor accepted the sub-subcontractor’s work as complete and paid for the work in full.  The subcontractor on the other hand argued that the statute of limitations began to run when the entire project was completed and accepted by the owner.  The subcontractor relied on the Florida Supreme Court’s opinion in Fed. Ins. Co. v. Southwest Florida Retirement Ctr., Inc., 707 So. 2d 1119, 1121 (Fla. 1998), which stated that Section 95.11 “as it applies to an action on a performance bond, accrues on the date of acceptance of a project as having been completed according to the terms and conditions set out in the construction contract.”
 

Continue Reading...

Court Rules Lien Timely Filed Pursuant to Florida Statute 713.08(5)

J.S.L. Constr. Co. v. Levy, 994 So.2d 179 (Fla. Dist. Ct. App. 2008)

In this case, a homeowner sued a contractor to discharge a mechanic's lien and for breach of contract.  The contractor was hired to construct the shell of a residence, with non-shell work performed by change order.  Among other things, this case addresses whether the contract recorded its claim of lien timely.

Florida Statutes Section 713.08(5) provides that a "claim of lien may be recorded at any time during the progress of the work or thereafter but not later than 90 days after the final furnishing of the labor or service or materials by lienor."  The parties had agreed that the contractor would oversee work performed by electrical and other subcontractors.  Moreover, because the subcontractors' permits were tied to the master permit, the contractor could not close out its permit and complete the project until the electrical and other subcontract work was performed.  The contractor also did a final walk through of the project with the building inspector.  Because the contractor filed its claim of lien within 90 days of those activities, the claim of lien was timely.

Insurer Granted Summary Judgment against General Contractor where Contract between Subcontractor and Injured Worker's Firm Fails to Meet Indemnification Requirements

Connolly Bros., Inc. v. Nat’l Fire & Marine Ins. Co., Civ. No. 06-11673-NG, 2008 WL 5423198 (D. Mass. Sept. 30, 2008)

In this case, the Federal District Court for the District of Massachusetts granted an insurer’s motion for summary judgment on a general contractor’s claim for indemnification and for unfair and deceptive practices under M.G.L. c. 93A, because the general contractor was not covered for the relevant incident by the insurer’s policy.

Continue Reading...

Inability to Determine Whether Owner Owed General Contractor when Subcontractor filed Lien Precludes Summary Judgment

In Nitro Dynamics v. Petruzzi Bros., Inc., 2008 WL 4635884 (Mass. Super. Ct. Sept. 26, 2008)

In this case, a subcontractor sued three defendants - the owner, the general contractor, and a surety - asserting claims for breach of contract, quantum meruit, and for recovery on a mechanic’s lien dissolution bond.  The Superior Court granted the owner’s motion for judicial notice of a stipulation of dismissal in a related action, but denied the owner’s motion for summary judgment.

Continue Reading...

Finding Surety Sufficiently Pled for Quia Timet, Court Denies Motion to Dismiss

Safeco Ins. Co. of America v. Tarragon Corp., 2008 WL 427969 (M.D. Fla. Sept. 16, 2008)

In Safeco, a third-party sued a general contractor and a surety in state court to recover against a Section 713.24 lien transfer bond.  Because the contractor refused to honor its obligations to the surety under their indemnity agreement, the surety then sued the contractor in federal court, asserting a claim quia timet, based on the future monies that the third-party was demanding on the bond.  Quia timet allows a person to seek equitable relief from future probable harm to a specific right.  Under Florida law, quia timet relief is not appropriate without proof that the surety realistically faces loss under the bond and is in jeopardy.

Continue Reading...

The Class of One Theory of Equal Protection has No Application in the Public Hiring Context

Douglas Asphalt Co. v. Qore, Inc., 541 F.3d 1269 (11th Cir. Sept. 2, 2008)

In Douglas Asphalt, a highway paving contractor sued State Department of Transportation officials, in their individual capacity, under 42 U.S.C. Section 1983.  The contractor claimed that the Department wrongfully singled out the contractor and treated it differently than other paving contractors in violation of the equal protection clause.  The contractor argued that the officials were not shielded from liability by their qualified immunity defense because the contractor was alleging a “class of one” equal protection claim.

The Eleventh Circuit disagreed and held that the reasoning behind the U.S Supreme Court’s 2008 decision in Engquist v. Oregon, 128 S. Ct. 2146 (2008), a government-employee relationship case, applied in the government contractor context.  Specifically, there is a “crucial difference between the government exercising its power to regulate or license, as lawmaker, and the government acting as proprietor to manage its internal operation.”  Employment decision making, including the hiring of government contractors, is “often subjective and individualized, resting on a wide array of factors that are difficult to articulate and quantify.”  Thus, the class of one theory of equal protection has no application in the public hiring context—otherwise every government hiring decision would become a constitutional matter.

Contractor Authorized by Condo Association to Work on Common Areas May Sue Association as Unit Owners' Representative

Trintec Constr., Inc. v. Countryside Village Condo. Assoc., 992 So. 2d 277 (Fla. Dist. Ct. App. 2008)

This case addresses whether the term “owner” for the purpose of applying mechanic’s lien law to a condominium property and improvements to its common elements refers to:  (a) each and every unit owner in the condominium, or (b) the condominium association created by the declaration.  The association argued that lien law’s use of “owner” means each individual condominium owner such that those owners are indispensable parties.  The Court, analyzing the construction lien statute and Florida civil procedure rules as to condominium associations held that the unit owners are not indispensable parties and the roofing contractor could proceed against just the association.

Continue Reading...

Contracts Cancelled Because of Illegal Actions May be Unenforceable

FCI Group, Inc. v. City of New York, 2008 WL 2796591 (N.Y. App. Div. July 22, 2008)

In this case, plaintiff contractor sued to recover the outstanding balance for work already completed on a construction project after the city cancelled the contract because of plaintiff’s attempted bribery of two city officials.  The Appellate Division, First Department, granted defendants’ motion for summary judgment, holding that:  (i) “plaintiff agreed to conduct itself ethically…and consented to the imposition of penalties for violating the contractual prohibition against dispensing monetary inducements to City workers;” and (ii) the illegal conduct at issue was central to plaintiff’s performance under the contract.

The court rejected defendants’ alternative argument that the contract’s alternative dispute resolution clause required dismissal in favor of arbitration.  The court held that the narrow ADR provision only applied to specified disputes in accordance with the intent of the parties and could not be interpreted so as to render the language limiting its scope mere surplusage.

Washington's Limited Liability Company Act is Applicable Retroactively and Permits Liability for Individual LLC Members or Managers

Emily Lane Homeowners Ass’n v. Colonial Dev., LLC, 139 Wash. App. 315, 160 P.3d 1073 (2007)

In this case, Emily Lane Homeowners Association sought damages against Colonial Development, LLC and its individual company members and managers.  Emily Lane alleged that members of Colonial failed to act in a timely manner to address warranty claims.  When Emily Lane filed suit on July 19, 2005, Colonial had already dissolved and filed a certificate of cancellation.  The trial court granted summary judgment, finding that Emily Lane’s action against Colonial could proceed even though Colonial had already dissolved.  However, the trial court also dismissed Emily Lane’s claims against the members and managers of Colonial, presumably finding that they were immune from liability as individuals.

On appeal, there were two main issues.  First, whether the 2006 amendment to Washington’s Limited Liability Company Act, RCW 25.15, could be applied retroactively to permit an action against a dissolved limited liability company (LLC).  Second, whether members and managers of a company could personally be liable under the Limited Liability Company Act if they did not properly wind up the dissolution of the LLC. Continue Reading...

Finding No Bad Faith, Court Enforces Termination for Convenience and Conversion Provisions Included in Parties' Contract

Stony Brook Constr. Co. v. Coll. of N.J., 2008 WL 2404174 (N.J. Super. Ct. App. Div. June 16, 2008)

This appeal arose out of a lawsuit filed by a contractor, Stony Brook Construction Co. and its surety, Fidelity & Deposit Company of Maryland (F & D), against The College of New Jersey (TCNJ), in connection with the construction of a new three-story building on the TCNJ campus.  In August 1998, TCNJ entered into multiple prime contracts for the construction.  TCNJ retained Stony Brook to perform the general construction work for its bid price of $3,783,565.  The anticipated completion date for the project was August 17, 1999.  TCNJ retained a construction management firm, CMM, to coordinate and schedule the project.  Two TCNJ employees (Rogers and Bressler) were also designated as project supervisors.  Due to numerous delays and disagreements between the parties, the project remained unfinished as of the anticipated completion date.

In October 1999, TCNJ terminated its contract with Stony Brook for nonperformance.  On November 5, 1999, TCNJ and F & D executed a takeover agreement, by which F & D agreed to complete the work in exchange for the unpaid balance of the contract price.  Problems continued, and in September 2000, F & D ceased performance, claiming that TCNJ breached the takeover agreement.  TCNJ hired another contractor to complete the general construction. Continue Reading...

Pay-When-Paid Clause Does Not Shift Risk of Non-Payment to Subcontractor

Otis Elevator Co. v. Hunt Constr. Group, Inc., 859 N.Y.S.2d 850 (N.Y. App. Div. 2008)

In this case, plaintiff subcontractor sought damages resulting from an alleged breach by defendant general contractor for payments due under the subcontract.  Both parties moved for summary judgment.  Defendant argued that its receipt of payment from the owner was a condition precedent to its obligation to pay plaintiff, and that it was under no obligation to pay because it had not yet received payment from the owner.  The court rejected this argument, holding that “the pay-when-paid clause in the subcontract merely regulated the time of payment, and did not shift the risk of owner nonpayment to plaintiff.”  Because plaintiff submitted evidence establishing its entitlement to payment, plaintiff’s motion for summary judgment was granted, and defendant’s motion was denied.

Showing that Adequate Safety Devices were Absent is Sufficient to Establish Prima Facie Liability under NY Labor Law ยง240(1)

McCarthy v. Turner Constr., Inc., 859 N.Y.S.2d 648 (N.Y. App. Div. 2008)

In this case, plaintiff brought claims under Labor Law §240(1) for injuries sustained when the unsecured ladder he was standing on to drill holes in the ceiling tipped over and he fell to the floor.  The Supreme Court granted summary judgment to plaintiff on the issue of liability under the Labor Law and the Appellate Division, First Department, affirmed.

The court held that, for purposes of establishing a prima facie case of liability under the statute, the plaintiff need only show that adequate safety devices to prevent the ladder from slipping were absent; plaintiff is not required to show the ladder was defective.  Further, the owner and general contractor would still be liable even if the apprentice electrician working with plaintiff disobeyed an instruction to hold the ladder steady, as this is not the type of “safety device” contemplated by the statute.

Self-Performance by General Contractor Forbidden under New Jersey Community College Contracts Law

D.A. Nolt, Inc. v. Camden County Coll., 2008 WL 2277095 (N.J. Super. Ct. App. Div. June 5, 2008) (Unpublished) 

In this case, a general contractor sued its client for breach and sought declaratory judgment when the college refused to allow the general contractor to self-perform work that had been assigned to a Small Business Enterprise (SBE) in the construction bid.  The trial court granted summary judgment in favor of the college and dismissed the complaint.  On appeal, summary judgment was affirmed.  The appellate court upheld the trial court’s conclusion that self-performance is equivalent to substitution of another sub-contractor because the result is the same – the subcontractor on the bid does not perform the work.  Moreover, both outcomes would thwart the aim of New Jersey County College Contracts Law (“CCCL”) to foster competitive bids by disallowing bid shopping.  As substitution of another contractor is not permitted under the CCCL, then similarly, self-performance by the general contractor is likewise not permitted.

Claims Against Architectural Firm Fell Under Professional Services Exclusion Based on Allegations of Underlying Complaints

Wimberly Allison Tong & Goo, Inc. v. Travelers Prop. Cas. Co., 2008 WL 2357863 (D.N.J. June 5, 2008)

In this case, plaintiff architectural firm sued commercial general liability (CGL) and excess liability insurers seeking damages and a declaratory judgment that insurers had a duty to defend it in the underlying suits, which arose from the collapse of a parking garage designed by plaintiff.  Both insurers denied coverage under provisions that excluded from coverage injuries arising out of plaintiff's provision of professional services.  Both sides moved for summary judgment.  The court granted summary judgment for the defendants finding that all the claims filed against plaintiff in the wake of the garage collapse fell within the professional services exceptions of both policies, based on the factual pleadings of each of the complaints.

Court Declines to Strike Defendant's Answer as Sanction for Spoliation of Evidence

Carroway Luxury Homes, LLC v. Integra Supply Corp., 859 N.Y.S.2d 834 (N.Y. App. Div. 2008)

In this case, plaintiff brought suit for construction delays and business expenses that arose after a forklift rented from defendant rolled over while being operated by plaintiff’s subcontractor.  Defendant answered asserting affirmative defenses and counterclaims.  Plaintiff moved to strike defendant’s answer based on intentional spoliation of evidence, asserting that defendant had sold the forklift at issue before plaintiff had the opportunity to examine it.  The court denied plaintiff’s motion, holding that striking a pleading is a drastic sanction and that the record, at that time, was insufficient to determine whether the unavailability of the forklift for examination would deprive the plaintiff of the means to prove its case.

Trial Court Erred in Granting Summary Judgment in Favor of School District on Claims Stemming from Completion Contract

Los Angeles Unified Sch. Dist. v. Great Am. Ins. Co., 163 Cal. App. 4th 944 (2008)

In this case, the District had contracted with a construction company to build a new elementary school for approximately $10.1 million.  Unsatisfied with the work, the District adopted a declaration of emergency under Public Contract Code § 20113, allowing the District to enter into a completion contract without inviting bids.  Defendant Hayward Construction Company was awarded the contract and Great American Insurance Company issued a performance bond for $4.5 million.  In the completion agreement, Hayward guaranteed that the maximum amount payable by the District for the cost of the work plus the contractor’s fee would not exceed $4.5 million.  Hayward’s scope of work included items listed on two “pre-punch lists,” identifying the remaining work to be completed or corrected.

Hayward subsequently informed the District that unforeseen circumstances concerning work that was not included in either of the pre-punch lists required an increase of the contract price beyond the contract maximum.  Payment was made to Hayward under a separate agreement preserving the District’s right to recover the money from all responsible parties, including Hayward and its surety.  When Hayward and its surety refused the District’s demand for return of more than $1 million, the District filed a complaint for breach of contract, breach of performance bond and declaratory relief.  Hayward cross-claimed for breach of contract, rescission and declaratory relief. Continue Reading...

Sureties Are Not Necessary Parties under FRCP

D&D Assocs., Inc. v. N. Plainfield Bd. of Educ., 2008 WL 2277121 (D.N.J. June 2, 2008)

In this case, the court addressed whether a surety company was a necessary party under Fed. R. Civ. P. 19(a) and whether a motion to amend the pleadings to include the surety was untimely, prejudicial and futile.  D&D Associates had sued the Board of Education to recover the contract balances owed in connection with work on a school construction project.  Almost five years after commencing the lawsuit, the Board sought to amend their answer to join the surety, American Motorists Insurance Company, to the litigation.  The court denied the motion on the grounds that sureties are not necessary parties, and because it was untimely, prejudicial, wasteful and futile to join the party at such a late stage of litigation.

Court Grants Surety Summary Judgment on Issue of Indemnification Where Defendant Provided "Not a Shred of Evidence" to Contravene Surety's Showing of Good Faith

Great American Ins. Co. v. Gen. Contractors & Constr. Management, Inc., 2008 WL 2245986 (S.D. Fla. May 29, 2008)

In this case, a surety company sought indemnification from a contractor under a payment bond.  The surety had paid claimants under the bond and argued that it was contractually entitled to reimbursement.  The contractor argued that the surety failed to bear its alleged initial burden of proving that the surety paid the claims in good faith.  The Court held that the surety’s initial burden was satisfied by evidence that the surety had indeed paid claims under the bond.  Thereafter, it was then the contractor’s burden to provide contradictory evidence or evidence that the surety paid the claims in “bad faith.”

It is well settled in Florida that a surety’s bad faith is the only defense to a surety’s indemnity claim.  Therefore, Florida courts will uphold a surety’s contractual right to indemnification so long as the surety acted on a good faith belief that it was required to act or pay, regardless of whether any liability existed.  To establish a surety’s bad faith, the contractor must demonstrate that the surety acted “with deliberate malfeasance”—meaning that that surety intentionally and wrongfully acted without legal right.  A lack of due diligence or negligence is not the equivalent of bad faith and even “gross negligence” is not the same as bad faith.

Finding Two Year Statute of Limitations Applied, Court Rejects Claim for Professional Negligence

Baker County Med. Svcs., Inc. v. Summit Smith, 2008 WL 2245587, Case 3:05-cv-541-J-33HTS (M.D. Fla. May 29, 2008)

In this case, an owner sued a contractor under a design-build contract, alleging that the contractor breached the contract by failing to fulfill its implied duty to perform according to established industry and professional standards.  While Florida law permits such “professional negligence” actions to be pled as a breach of contract or a tort, such an action must be brought under the more specific two year professional malpractice statute of limitation, not the general four year limitation for actions based on “design, planning, or construction of an improvement to real property.”

Court Finds Lien did not Attach Absent Parties' Meeting of the Minds

Niehaus v. Big Ben’s Tree Svc., Inc., 982 So. 2d 1253 (Fla. Dist. Ct. App. 2008)

In this case, the court held that a contractor’s lien under Section 713.05 never attached because the parties never had a meeting of the minds as to a material term of their contract.  The owner had contacted a contractor to cut down and “remove” a tree.  The owner believed that “remove” meant that the tree would be taken from her property, but the contractor intended for remove to have its technical meaning in the tree industry, which is to simply move the tree.  The owner refused to pay the contractor when he would not take the tree from her property, resulting in the contractor recording a mechanic’s lien under Section 713.05.

A mechanic’s lien can only attach when a valid contract exists, and parties’ must agree as to material terms for there to be a valid contract.  The court found that “removal” was a material term of the parties’ contract in this case, and that they had different understandings as to the term’s meaning.  Therefore, the contractor’s lien never attached, and the owner was entitled to attorney’s fees under Section 713.29 for her successful defense against the lien.

Damages Awards for Delay in Construction of Home and Alternate Living Arrangements Were Not Impermissibly Duplicative

Fisher Island Holdings, LLC v. Cohen, 983 So. 2d 1203 (Fla. Dist. Ct. App. 2008)

In this residential construction case, an owner entered into a short-term lease because of substantial delays in the completion of his single family home.  The owner sued the contractor for delay, and the jury awarded the owner both delay damages and damages for alternative living arrangements.  The appellate court held that this was not a double recovery.  The jury permissibly awarded delay damages (measured by the rental value of the building under construction during the delay period) for the period of the contractor’s delay up to the commencement date of the owner’s nine month lease.  The jury then awarded alternative living damages for the duration of the lease.

Exclusion of Coverage for Claims Arising from Breach of Contract Includes All Claims with Substantial Nexus to Breach or Having "But For" Relationship with Breach

N. Plainfield Bd. of Educ. v. Zurich Am. Ins. Co., 2008 WL 2074013 (D.N.J. May 15, 2008)

In this case, the Board of Education had been sued by various contractors and subcontractors for breach of contract and various tort claims, and sought specific performance from Zurich American Insurance Co. to defend against the claims under their insurance policy.  Zurich denied coverage, citing the policy provision excluding from coverage all claims arising from breach of contract.  The court found that that this exclusion covered any action that alleged a breach of duty, neglect, error, misstatement or omission and that grew out of or had substantial nexus with breach of contract, or any injury that would not have occurred but for the contract breach.  Thus, Zurich was justified in refusing coverage and indemnity for those claims, and the court granted Zurich’s motion for summary judgment against the Board.

Surety Found Not Liable for Attorneys Fees without Express Provision in Bond

Titan Stone, Tile & Masonry, Inc. v. Hunt Constr. Group, Inc., 2008 WL 2038857 (D.N.J. May 12, 2008)

In this case, the court ruled on a motion for reconsideration of a finding that a subcontractor who defaulted on performance, but not the surety, was responsible for the attorneys fees of the general contractor, Hunt Construction Group.  The court applied the principle that a surety can be held liable only in accordance with the strict terms of its undertaking, and found that the surety bond in this case did not specifically provide for reimbursement of attorneys fees.  Hunt argued that the obligations of Titan under the performance bond should be coextensive with those of Titan under the agreement.  The court rejected this argument as inconsistent with the purpose of a performance bond, which is to provide the general contractor with the funds to complete the project upon the default of the subcontractor, not to make the general contractor whole.

Court Holds Claims Arising from Zoning Violations Subject to Professional Liability Exclusion, Insurer Not Obligated to Defend or Indemnify

W. World Ins. Co. v. Azoff, Civ. No. 07-00494-BLS2, 2008 WL 4107481 (Mass. Super. Ct. May 15, 2008)

In this case, the Superior Court granted an insurer’s motion for summary judgment and denied the insured contractor’s cross-motion for summary judgment, holding that the insurer was not obligated to defend or indemnify the contractor for a claim brought against it in a separate action, because the claim fell under a professional liability exclusion in the relevant policies.

Continue Reading...

Court holds Surety has Common Law Claim for Indemnity Against Subcontractor, Despite Absence of Privity

J.C. Gibson Plastering Co. v. XL Specialty Ins. Co., 2008 WL 1931348 (M.D. Fla. May 2, 2008)

In J.C. Gibson Plastering, the U.S. District Court for the Middle District of Florida held that a surety could state a claim for common law indemnity against a subcontractor despite the absence of privity.  The court found that the two elements necessary to state a claim for common law indemnity were satisfied:  (i) the surety may be constructively, vicariously or derivatively liable for the subcontractor’s failure to pay sub-subcontractors, and (ii) the surety was without fault in causing the loss it was required to bear, despite failing to timely respond to the claim.

Also, despite the lack of Florida authority on the question, the court also held that a surety’s failure to respond to the subcontractor’s claim for payment under a payment bond within forty-five days (as required under the bond) barred the surety from challenging the claim or from asserting counterclaims to the extent the surety could have reasonably identified the bases of its affirmative defenses or counterclaims’ during the forty-five day period.  By failing to respond timely, the claim was undisputed and subject to summary judgment.

Statute of Limitations for Contractor Negligence and Breach of Warranties Does Not Accrue until Turnover of Control of Condo Association to Unit Owners

Saltponds Condo. Assoc. v. Walbridge Aldinger Co., 979 So. 2d 1240 (Fla. Dist. Ct. App. 2008)

In this case, a condo association sued a contractor in connection with alleged construction defects discovered after the control of the association passed from the developer to the unit owners.  The contractor argued that the claims were barred by the three-year “statute of limitations” set forth in Florida Statute Section 718.203.  That Section, however, merely sets the warranty period for construction improvements and materials, not the statute of limitations.

Continue Reading...

Under Business and Professions Code ยง 7031, Contractor Must be Licensed Prior to Preparing Shop Drawings or Ordering Materials for Construction Project

Great West Contractors, Inc. v. WSS Ind. Constr., Inc., 162 Cal. App. 4th 581 (2008)

WSS Industrial Construction, a steel subcontractor, sued general contractor Great West Contractors, to recover for work performed on a public works project in Riverside, California.  At the time that WSS submitted its bid proposal to Great West, WSS had applied for but not yet obtained a corporate contractor’s license.  WSS did receive a license after the bid was accepted, but only after it had already ordered multiple sets of shop drawings and some of the material necessary for the project.  WSS initiated the lawsuit by suing Great West and its surety, Fidelity and Deposit Company of Maryland, for $91,000 due under the contract and subsequent change orders.

At trial, Great West and Fidelity moved for a nonsuit on the grounds that WSS was statutorily barred, pursuant to Business and Professions Code section 7031, from any recovery because WSS was not duly licensed at all times during performance of the contract.  The trial court determined that WSS’s president had held valid individual licenses at all times and that, in any event, WSS was not required to have a license for the work that it performed prior to receiving its license.  The court held that “there was substantial compliance with the licensing during the contract and work was performed in good faith.”  The jury awarded WSS $220,000 in damages, including statutory penalties and interest.  Great West and Fidelity appealed after the court rejected their post-trial motions for a new trial, vacation of judgment and judgment notwithstanding the verdict. Continue Reading...

Appellate Court Finds Liquidated-damages Clause Was Not a Penalty and Thus Was Enforceable

Mineo v. Lakeside Village of Davie, LLC, 983 So.  2d 20 (Fla. Dist. Ct. App. 2008)

Where a contract for the purchase of real property and construction of a residence gave the seller the option of retaining deposits and change order payments as liquidated damages in the event of the buyer’s default, or the seller could sue for specific performance at the purchase price plus interest as delay damages, the liquidated damages provision was not an unenforceable penalty because the contract did not provide the seller with the option to sue for actual damages (which would have change the character of the forfeiture as agreed damages).

Subcontractor's Contractual Indemnity Obligation to Contractor for EIFS Damage Not Covered by Indemnity Provisions of Texas Product Liability Act

K-2, Inc. v. Fresh Coat, Inc., 253 S.W.3d 386 (Tex. App. 2008)

In this case, the court held that the Texas Product Liability Act did not provide a product seller with the right of indemnity against a product manufacturer for that seller’s independent liability under a contract.

Several homeowners sued their builder, its subcontractor which installed synthetic stucco cladding (EIFS) on their houses and the EIFS manufacturer after experiencing water penetration leading to structural damage.  After the claims made by the homeowners and the home builder against the subcontractor were settled, the subcontractor obtained a judgment against the manufacturer for indemnification of the amounts it paid in the settlement.  The manufacturer appealed that portion of the judgment finding it liable to indemnify the subcontractor for the amount it paid to settle the home builder’s claims because it was paid under an indemnity clause in the subcontract. It did not dispute that part of the judgment obligating it to indemnify the subcontractor for settlement of the homeowners’ claims.  Continue Reading...
Tags:

Insurer's Duty to Defend Construed Broadly in Favor of Insured

WTC Captive Ins. Co. v. Liberty Mut. Fire Ins. Co., 549 F. Supp. 2d 555 (S.D.N.Y. 2008)

After the World Trade Center disaster in September 2001, the City of New York created a captive insurance company, funded by a grant from the Federal Emergency Management Agency, to insure the costs of lawsuits arising from the WTC clean-up efforts.  Liberty Mutual was the primary insurer and had agreed to defend and indemnify the city against claims including, but not limited to, bodily and personal injury.  A group of secondary insurers agreed to provide the same coverage if the Liberty Mutual policy became exhausted.  All of the policies were retroactive to September 11, 2001. Continue Reading...

Constructive Notice Not Established by Discussion in Meetings

Geonie v. O.D. & P. N.Y., Ltd., 855 N.Y.S.2d 495 (N.Y. App. Div. 2008)

An injured worker, Geonie, filed a negligence suit against multiple defendants, including the general contractor, after stepping into an opening left by the removal of a tile from a raised floor in a computer room.  Geonie argued that defendants failed to provide adequate safety devices to protect against an elevation-related hazard and failed to adequately supervise the work area.  He further claimed that because the removed tile was discussed at weekly safety meetings, the defendants had, at least, constructive notice of the problem.  The trial court dismissed Geonie’s claims under New York Labor Law and his negligence claim against the general contractor. Continue Reading...

Landscaper Must Have Proper License to Recover Damages for Breach of Contract

Hakimi v. Cantwell Landscaping & Design, Inc., 855 N.Y.S.2d 273 (N.Y. App. Div. 2008)

Hakimi filed a breach of contract claim against Cantwell stemming from landscaping work performed on the property where Hakimi was having a new home built.  Cantwell admitted that it was not licensed as a home improvement contractor at the time it did the work.  In response to the lawsuit suit, Cantwell filed a mechanic’s lien and a notice of pendency against Hakimi’s property.  Cantwell claimed that it did not need a home improvement contractor’s license because Hakimi was building a new house and the administrative code exempted new home construction from the home improvement licensing requirements.  Hakimi moved to dismiss Cantwell’s counterclaims and the Supreme Court denied the motion. Continue Reading...

Federal Arbitration Act Does Not Preempt California Code of Civil Procedure ยง 1281.2; California Court May Refuse to Enforce Arbitration Agreement To Prevent Possibility of Conflicting Rulings

Best Interiors, Inc. v. Millie and Severson, Inc., 2008 WL 1122182 (Cal. Ct. App. Apr. 11, 2008)

A dispute arose between general contractor Millie and Severson, Inc. and subcontractor Best Interiors, Inc. related to the construction of a hospital in Whittier, California.  Best sued M&S, the hospital and two building inspectors, alleging various delay and disruption damages caused by improper management and inspection of the project.  M&S petitioned to compel arbitration of the dispute and to stay Best’s lawsuit, based on arbitration clauses in the subcontract and the prime contract.  Best opposed on the grounds that (1) the building inspectors could not be compelled to arbitrate; (2) the arbitration might result in inconsistent results; and (3) the court had authority under California Code of Civil Procedure § 1281.2 to refuse to enforce the arbitration clause.  The trial court granted Best’s petition.  On appeal, M&S raised two arguments.  First, M&S argued that the Federal Arbitration Act, 9 U.S.C. § 1 et seq., applied to the arbitration agreement and did not give the trial court discretion to deny arbitration.  Second, M&S argued that, even if California law applied to the arbitration agreement, there was no possibility of conflicting rulings. Continue Reading...

Whether Liquidated Damages Clause is Properly Invoked Depends on Whether Actual Damages Can be Determined

Zeer v. Azulay, 2008 WL 1134239 (N.Y. App. Div. Apr. 8, 2008)

In this case, defendant contractors agreed to construct a home on property owned by plaintiffs pursuant to a written contract executed by the parties in September 2003.  The parties agreed that if the contractor did not complete the project by February 29, 2004 and obtain a certificate of occupancy, it would be liable for liquidated damages of $250 per day until the work was completed. Continue Reading...

No Summary Judgment Where Counterclaim is Equal To or Greater Than Amount Demanded in Complaint

Pronti v. Grigoriou, 853 N.Y.S.2d 718 (N.Y. App. Div. 2008)

In this case, a construction company filed a mechanic’s lien foreclosure action against a homeowner.  The parties had executed a written contract providing that Pronti would find an independent contractor to install vinyl siding on Grigoriou’s residence.  After Grigoriou paid the full contract price of $11,000, she refused to pay a $500 cleanup fee provided for in the contract.  Grigoriou alleged that Pronti performed the work in an “unworkmanlike manner” and counterclaimed for $10,520 in damages. Continue Reading...

Economic Loss Doctrine may not Preclude Claims Against Building Contractors for Negligent Construction that Results in Foreseeable Damage to Property

Harris v. Suniga, 344 Or. 301, 180 P.3d 12 (Or. 2008)

In this case, the defendant general contractors constructed an apartment building for a California investment company.  The California investment company sold the completed apartment building to the plaintiffs, trustees for the Harris Family Trust.  Following the sale, plaintiffs found the apartment building had problems with leaking water and dry rot and filed a claim for negligent construction against the defendant contractors.  Prior to suit, the plaintiff and defendants were “strangers.”  The plaintiffs did not purchase the apartment building from the defendants, did not contract with the defendants, and did not have any previous contact with the defendants.  Plaintiffs alleged that defendants’ failure to install required flashings in the building caused the dry rot damage, and that the failure constituted negligence.

Continue Reading...
Tags:

Suit Can Proceed Against General Contractor Based on Claims of Subcontractor's Negligence and Public Nuisance

New York v. Shaw Contract Flooring Servs., 853 N.Y.S.2d 694 (N.Y. App. Div. 2008)

State university brought claims against a general contractor and subcontractor for asbestos released as a result of tile work performed by the subcontractor.  The trial court denied the general contractor’s motion to dismiss the negligence and public nuisance claims.  The Appellate Division affirmed. Continue Reading...

General Contractor Waives Right to Challenge Settlement by Surety

Kennerson v. LaBarbera, 536 F. Supp. 2d 305 (W.D.N.Y. 2008)

In this case, a subcontractor sued a general contractor and a surety for failure to make payments for work performed on a construction project for a county water authority.  The surety filed cross-claims against the general contractor pursuant to an indemnification agreement.  The water authority asserted indemnification claims against the surety.  The surety subsequently settled the claims against the general contractor and moved for summary judgment as to all cross-claims.  The district court granted the motion. Continue Reading...

Bond Issuer Lacks Authority to Release Claims Related to Construction

Eaton Elec., Inc. v. Dormitory Auth. of New York, 852 N.Y.S.2d 363 (N.Y. App. Div. 2008)

In this case, plaintiff contracted with Dormitory Authority of New York to perform electrical work in the renovation of a library.  Plaintiff experienced delays and financial problems, eventually forcing it to assign its payment interest in the construction contract to AXA Global Risks U.S. Insurance Company in exchange for financial assistance.  Later, in return for payment from Dormitory Authority, AXA executed a release to discharge Dormitory Authority from any claims of liability in relation to the underlying construction project.  That release later became problematic when plaintiff sought an additional $12 million from Dormitory Authority as reimbursement for unanticipated and unforeseen additional costs incurred on the project.  Dormitory Authority moved for summary judgment, arguing that AXA had released it from any such liability.  The Supreme Court denied Dormitory Authority’s motion, reasoning that AXA lacked authority to release any such claims. Continue Reading...

Builder Liable for Intentional Infliction of Emotional Distress and Consumer Protection Act Violations Based on Verbal Abuse of New Home Purchasers

Lepp v. V.M.S. Realty Trust, 2008 WL 375971 (Mass. App. Div. Feb. 8, 2008)

This is a per curiam decision by the Massachusetts Appellate Division that addresses the liability of homebuilders and vendors.  In Lepp, the purchasers of a newly built home sued the vendor of the home for breach of contract for failure to install the agreed upon insulation.  The purchasers also sued the builder, who was an employee of the vendor, for breach of contract, breach of the implied warranty of good workmanship, intentional infliction of emotional distress and violation of M.G.L. c. 93A — the Massachusetts Consumer Protection Act.  The trial court found for the plaintiffs on all counts in a jury-waived trial and the defendants appealed.
Continue Reading...

Kitchen Contractor Potentially Liable Under New Jersey's Consumer Fraud Act

CZAR, Inc. v. Heath, 939 A.2d 837 (N.J. Super. Ct. App. Div. 2008)

In this case, a homeowner brought claims against a custom kitchen contractor under New Jersey’s Consumer Fraud Act.  During the construction of a new home, the homeowner had contracted directly with a custom kitchen contractor for the installation of custom kitchen cabinets, interior doors, a front door, and certain moldings.  The trial concluded that the home improvement practice regulations found in N.J.A.C. 13:45A-16.1 to 16.2 were not applicable to plaintiff and, therefore, dismissed the CFA claims.  The trial court reasoned that the kitchen contractor's work was not a “home improvement” within the meaning of the regulation because the construction and installation of the doors, cabinets, and moldings were part of the construction of a new residence and, therefore, excluded from the definition of “home improvement.”

Continue Reading...

General Contractor Cannot Bring Direct Action Against Subcontractor's Insurer Regardless of General Contractor's Status as Additional Insured Under Subcontractor's Policy

Ohio Cas. Ins. Co. v. Time Warner Entm’t Co., L.P., 244 S.W.3d 885 (Tex. App. Feb. 6, 2008)

In this case, a general contractor brought a declaratory judgment action against its subcontractor’s primary and umbrella insurers to recover the cost of removing and replacing fiber optic cable that the subcontractor installed improperly.  Although the trial court granted summary judgment in favor of the general contractor, the Dallas Court of Appeals reversed.
Continue Reading...
Tags:

Texas Statute Bars Property Owner's Liability for Injury to Independent Contractors

Vanderbeek v. San Jacinto Methodist Hosp., 246 S.W.3d 346 (Tex. App. 2008)

A plumber working on a remodel project for San Jacinto Methodist Hospital cut and capped a drainage pipe from a sink in an adjacent room.  Although he instructed a hospital employee that the sink was out of order and should not be used, hospital employees poured a drain cleaner into the sink when it wouldn’t drain.  When the plumber returned to remove the drainage line cap, a caustic liquid came out of the pipe, causing him chemical burns.  He sued the hospital for negligence for allowing caustic drain cleaner into the sink when he had given notice it was not to be used. Continue Reading...
Tags:

Owner Potentially Liable for Fraud and Consumer Protection Act Violations Based on False Promises of Payment

Atlantis Int’l Constr. Servs., Inc. v. Sluggo, LLC, 71 Mass. App. Ct. 1106 (2008) (Unpublished)

In this unpublished decision, the Massachusetts Appeals Court held that an owner could be held liable for fraud, breach of contract and violation of the Massachusetts Consumer Protection Act (M.G.L. c. 93A) for inducing a general contractor continue work based on the promise that the general contractor’s numerous disputed change order requests would be paid in full.  After completion of the project the owner refused to pay many of the general contractor’s change orders. Continue Reading...

Municipal Authority's Claim Against Surety for Bad Faith Falls Short

Intercon Constr., Inc. v. Williamsport Mun. Water Auth., 2008 WL 239554 (M.D. Pa. Jan. 28, 2008)

This case involved standard breach of contract claims and counterclaims between a general contractor and a public municipal authority.  In addition, the municipal authority also sued a performance bond surety on claims of bad faith. The municipal authority alleged that the manner in which the surety investigated and denied coverage under the performance bond, and its withholding of certain information from the authority, constituted bad faith under the Pennsylvania bad faith insurance statute. Continue Reading...

Insurer May Intervene Where it Has Legitimate Interest as Judgment Creditor in Outcome of Litigation

U.S. Fid. & Guar. Co. v. E. Contractors, Inc., 2008 WL 190758 (D. Mass. Jan. 15, 2008)

In this case, the Federal District Court for the District of Massachusetts issued an order on a Motion to Intervene and Dissolve Attachment.  The motion to intervene was allowed and the petition for dissolution was allowed in part and denied in part.  Plaintiff was an issuer of security bonds and defendant was a construction company.  Plaintiff issued a series of bonds to secure defendant’s performance on several construction projects.  Defendant defaulted on the projects and subsequently plaintiff successfully secured an ex parte attachment of four of defendant’s properties.  Another insurance company that had also entered into surety agreements with the defendant previously secured a judgment against the defendant for $8,342,233.27.  This judgment was never satisfied due to defendant’s insolvency.  The insurance company claimed an interest in the attached properties. Continue Reading...

Issue of Fact Precludes Summary Judgment in Indemnification Action

Ins. Co. of New York v. Central Mut. Ins. Co., 850 N.Y.S.2d 56 (N.Y. App. Div. 2008)

In this case, the First Department examined cross-motions for summary judgment in relation to contractual indemnification.  Plaintiffs – the property owner and general contractor in a related personal injury action – brought this action against a subcontractor, S&S Construction Group.  Plaintiffs sought a declaration that S&S’s liability insurer, Central Mutual Insurance, was required to defend and indemnify plaintiffs in connection with the underlying action.  According to plaintiffs, the contract between the general contractor/plaintiff and S&S required S&S to obtain insurance covering plaintiffs. Continue Reading...

Court Examines Definition of Progress Payments in Connection with California's Prompt Payment Penalty Statute

Murray's Iron Works, Inc. v. Boyce, 158 Cal. App. 4th 1279 (2008)

In this case, the California Court of Appeal addressed whether the prompt payment penalty statute was properly applied against the owner and, in doing so, provided a definition for progress payments under the statute.

California requires that an owner pay its contractor any progress payment due as to which there is no good faith dispute within 30 days following receipt of a demand for payment.  If there is a good faith dispute between the owner and contactor, the owner may withhold no more than 150 percent of the disputed amount.  Any amount wrongfully withheld by the owner is subject to a penalty of 2 percent per month on the improperly withheld amount, in lieu of any interest otherwise due.  The prevailing party is also entitled to attorney’s fees and costs.  (Cal. Civ. Code § 3260.1.)  Other statutes establish similar requirements for progress payments between contractors and subcontractors (Bus. & Prof. Code § 7108.5) and for payment of retention (Cal. Civ. Code § 3260).

Continue Reading...

Contractor Escapes Negligence and Indemnity Liability

Luby v. Rotterdam Square, L.P., 850 N.Y.S.2d 252 (N.Y. App. Div. 2008)

In this negligence action, plaintiff sustained injuries when he fell over a transition flare of a handicapped ramp.  That ramp had been constructed by defendant Clifford H. Quay & Sons fourteen years earlier pursuant to a contract between Quay and another defendant, Rotterdam Square.  The architectural firm that designed the plans pursuant to which the ramp was constructed was also named as a defendant.  Two issues were at stake.

Continue Reading...

Court Rules Surety had Right to Settle Principal's Claims Against Owner, Grants Motion for Summary Judgment

Liberty Mutual Ins. Co. v. Aventura Eng’g & Constr. Corp., 534 F. Supp. 2d. 1290 (S.D. Fla. Jan. 8, 2008)

The U.S. District Court for the Southern District of Florida has interpreted Florida law as allowing a surety to settle not only an owner’s claims on a performance bond, but also the principal’s claims against the owner.  In Aventura Eng’g, a surety completed construction of a project pursuant to an owner’s demand against a performance bond.  The principal, a general contractor, had allegedly defaulted on its contract with the owner, and thereafter refused the surety’s demands for indemnification.  The surety eventually executed a settlement agreement with the owner, whereby the surety exercised its power of attorney to execute a release of all claims that the contractor had against the owner growing out of the bonded contract. 

Continue Reading...

Architects Do Not Owe Special Duty of Care to Construction Workers

Leyden v. Spaulding & Slye Co., Inc., 2008 WL 241085 (Mass. Super. Ct. Jan. 3, 2008)

In this case the Superior Court granted an architect’s motion for summary judgment on claims brought against it by a construction worker for personal injuries sustained when the worker fell through a collapsed sump pump grate.  The defendant architect argued it was entitled to summary judgment because it owed no duty of care to the plaintiff. Continue Reading...

General Contractor Recovers Final Payment on Public Contract, Even Though Subcontractor Violated Prevailing Wage Act

Worth & Co., Inc. v. Dept. of Labor & Ind., 938 A. 2d 239 (Pa. 2007)

In this case, the Supreme Court of Pennsylvania decided the appeal of a general contractor, whose final payment was being withheld by a public school district on account of the GC’s subcontractor’s failure to pay prevailing wages to its workers.  Under the authority of regulations issued by the Department of Labor & Industry’s prevailing wage division, the Department had instructed the school district to withhold final payment from the general contractor, because workers of the subcontractor remainied unpaid following the subcontractor’s default and eventual bankruptcy. Continue Reading...

Court Addresses Implied Warranty of Habitability in Condominium Context

Berish v. Bornstein, 71 Mass. App. Ct. 1101 (2007) (Unpublished)

In this unpublished decision, the Massachusetts Appeals Court addressed the implied warranty of habitability as applied to construction of a residential condominium development.  Plaintiffs, who were trustees of a condominium association, appealed from the trial court’s ruling that faulty window installation in the units was not a latent defect and that faulty chimney attachments were not a safety threat to condominium unit inhabitants.  Plaintiffs also challenged the judge’s findings that certain other claims were time-barred.  The defendants (the condominium developer, an original trustee of the condominium trust, and the general contractor) cross-appealed from the judge’s ruling on the timeliness of plaintiffs' claims for breach of the implied warranty of habitability and for negligence. Continue Reading...

"Waiver of Subrogation" Clauses Do Not Bar Actions Arising Out of Gross Negligence or Violation of Statute or Regulation

Am. Ins. Co. v. Siena Constr. Co., 2007 WL 4711517 (Mass. Super. Ct. Dec. 24, 2007)

In this case, the Superior Court considered two consolidated cases that both arose out of an explosion of a newly constructed building.  In both cases the plaintiffs were insurance companies acting as subrogees.  Defendants (general contractors and subcontractors) moved for summary judgment on the ground that recovery was barred by “Waiver of Subrogation” clauses found in the contracts.  The plaintiffs argued that the waiver of subrogation clause did not extend to damages caused by a defendant's gross negligence or its violation of a statute or regulation.  In addition, they argued that the subcontractors were not protected by the waiver of subrogation clause.

The original judge in the case held that analogous case law concerning exculpatory clauses supported a denial of defendants’ summary judgment motion.  The judge also held that, by its terms, the waiver of subrogation clause did not include subcontractors.  In the consolidated case, the new judge accepted the rulings of prior judge and the motions for summary judgment were allowed in part and denied in part.  Plaintiffs’ claims were allowed to proceed but as to defendants with valid waiver of subrogation clauses (contractors not subcontractors) recovery was limited to damages arising from defendant’s gross negligence, or negligence premised on a violation of statute or regulation.

Continue Reading...

Washington Supreme Court Re-Affirms Mike M. Johnson Rules Regarding Waiver of Contractual Claims Provisions

Am. Safety Cas. Ins. Co. v. Olympia, 162 Wash.2d 762, 174 P.3d 54 (2007)

The Washington Supreme Court affirmed summary judgment for the City of Olympia against American Safety Casualty Insurance Company where the contractor (whose rights the surety was pursuing) failed to comply with contractual notice procedures.  During construction, the contractor had written letters purporting to reserve its right to bring a claim at a later date.  The contractor defaulted, and the surety completed the job.  After completion, the surety presented Olympia with a Request for Equitable Adjustment.  Though Olympia expressed a willingness to enter into negotiations if the surety provided sufficient supporting documentation, Olympia ultimately rejected the surety’s claim for failing to comply with the contract’s claims provisions.  When the surety filed suit, the Thurston County Superior Court granted Olympia summary judgment, which was then overturned by Division Two. Continue Reading...

No Need for "Base of Operations" Within Municipality in Order for Contractor to be Subject to Business Privilege Tax

V.L. Rendina, Inc. v. City of Harrisburg, 938 A.2d 988 (Pa. 2007)

In this case, a plurality of the Pennsylvania Supreme Court held that a municipality may apply its business privilege tax to the gross receipts from construction work performed within its borders regardless of whether the contractor maintained a “base of operations” within the municipality.  Reversing a Commonwealth Court decision in favor of the construction company, the majority focused on whether the company’s activities in Harrisburg fell within the definitive of “business” contained in the City’s tax ordinance. Continue Reading...

Plaintiff Wins Recovery in Quantum Meruit for Heating and Cooling Services Provided

Capital Heat, Inc. v. Buchheit, 848 N.Y.S.2d 481 (N.Y. App. Div. 2007)

In this case, the court awarded recovery in quantum meruit to plaintiff for heating and cooling services it had provided at the defendant's residence.  The court explained that:  (i) by issuing invoices, (ii) the plaintiff established an expectation that it would receive payment for its services, (iii) the invoices established the reasonable value of those services, and (iv) the defendant did not dispute that the plaintiff performed the heating and cooling work in good faith or of acceptable quality.

Continue Reading...

Mechanic's Lien on Owner's Real Estate Not Precluded Where Contract is Made with Party Other than Owner, but with Owner's Consent

Madigan v. Trace Constr., Inc., 878 N.E.2d 568 (Mass. App. Ct. 2007)

In this case, the Appeals Court dismissed an action seeking discharge of several mechanics’ liens encumbering plaintiff’s real estate.  The plaintiff, who was the owner of the encumbered property, claimed that because the general contractors entered into contracts with a tenant of the plaintiff, not the plaintiff, it was inappropriate to encumber plaintiff’s real property with a mechanic’s lien.  The Appeals Court affirmed the Superior Court dismissal, holding that summary discharge of a mechanic’s lien by the court was inappropriate and that defendants were entitled to discovery. 

Continue Reading...

Court Denies Summary Judgment in Insurance Dispute Concerning Indemnification for Wrongful Death Claim

Grand Crossing, L.P. v. U.S. Underwriters Ins. Co., 2007 WL 4591989 (S.D.N.Y. Dec. 18, 2007)

This case concerned an insurance policy claim made for partial coverage of settlement in a wrongful death action based on a construction site fatality.  The Southern District of New York denied the parties' cross-motions for summary judgment. 

Continue Reading...

Court Strictly Interprets Notice Requirements in Construction Contract

Marcor Remediation, Inc. v. County of Broome, 847 N.Y.S.2d 702 (N.Y. App. Div. 2007)

In this case, defendant hired the plaintiff contractor to perform lead abatement work.  The contractor sued for breach of contract and quantum meruit, alleging that the county had failed to pay for work performed.  The terms of the contract prohibited plaintiff from bringing any action arising out of the contract unless plaintiff “strictly complied with all requirements relating to the giving of notices and information with respect to such claim . . . .”  The contract further required plaintiff to file a “verified, detailed statement” in order to claim that it performed revised work under the contract, as plaintiff claimed here.  Plaintiff appealed after the action was dismissed by the trial court.

The appellate court affirmed, finding that plaintiff had failed to provide a "verified, detailed statement."  The court explained:   “compliance with notice of claim provisions of a municipal contract constitutes a condition precedent to the commencement of an action for breach of contract which may only be avoided if the municipality acted in a manner that precluded the other party from complying.”

No Victory for Plaintiff Where Renovations Were Made in Good Faith

Baker v. City of Plattsburgh, 847 N.Y.S.2d 300 (N.Y. App. Div. 2007)

In this case, plaintiff sought recovery of property damages due to water runoff caused by a utilities renovation and paving project carried out by defendants on an adjacent property.  The Supreme Court granted defendants’ summary judgment motion, dismissing the causes of action against them alleging that water runoff caused property damage.  However, defendants’ motion papers did not specifically address the remaining causes of action for trespass, due process rights violations and zoning ordinance violations, and thus those claims remained.

Continue Reading...

Court Awards Attorneys' Fees in Breach of Contract Action

Fabcon East, LLC v. Steiner Bldg. Co. NYC, 848 N.Y.S.2d 267 (N.Y. App. Div. 2007)

In this case, the court upheld an award of damages and contractually-based attorneys’ fees to plaintiff, finding sufficient support for the conclusion that defendant had breached the parties’ construction subcontract and the implied covenant of good faith and fair dealing.  However, the court reduced the attorneys’ fee award in the amount of $19,250.50 -- the amount of fees incurred by plaintiff in a separate action commenced against it by a sub-contractor.  The court explained:  “the subcontract provision dealing with an award of contractual attorney’s fees to the prevailing party in a covered action did not include the New Jersey action, to which [defendant] was not a party.”

Subcontractor Forfeited Right to Damages by Abandoning Project Prior to Completion

Colin C&M Corp. v. Bacon Constr. Co., 2007 WL 4711503 (Mass. Super. Ct. Dec. 7, 2007)

In this case, the Superior Court considered a subcontractor’s claims against a general contractor and the general contractor’s counterclaims relating to a public high school construction project.  In finding for the general contractor, the court found that the subcontractor was not entitled to damages because it walked off of the project and therefore failed to comply in strict accordance with the subcontract.  Further, the court found that the general contractor was entitled to damages because it had to finish the subcontractor’s work and pay outstanding invoices to the subcontractor’s vendors. Continue Reading...

No Summary Judgment on Labor Law Claims Regardless of Whether Plaintiff's Work Was Performed in Furtherance of Contract

Butt v. Bovis Lend Lease LMB, Inc., 2007 WL 4260519 (N.Y. App. Div. 2007 Dec. 6, 2007)

In this case, plaintiff sued for common law negligence and Labor Law violations, seeking to recover for injuries allegedly sustained when he fell from ladder while plastering a ceiling beam of an interior stairwell at a public school.  Defendants included the City of New York which owned the premises, the Board of Education which operated and maintained the premises, the general contractor, and the construction manager.  Defendants moved to dismiss the Labor Law violations on summary judgment, arguing that the work the plaintiff was performing when he was injured was outside the scope of his contract, and thus was not covered by the Labor Law.  The court denied the motion, finding that such a defense only applied to the benefit of parties who did not have authority to supervise or control the work at issue.  The court explained that such a defense would not apply to the owner’s liability because injury to a worker may not be circumscribed by contract.  Further, conflicting evidence had been presented as to whether the work was outside the scope of the contract., and so the issue was not capable of resolution on summary judgment. 

Subcontractor Liable for Damages Caused by Equipment It Was Contractually Obligated to Provide at Construction Site

Urbina v. 26 Court St. Assocs., LLC, 847 N.Y.S.2d 67 (N.Y. App. Div. 2007)

This case involved causes of action for negligence, violations of Labor Law §§ 200, 240(1) and 241(6), and loss of consortium brought by an electrician, Urbina, and his wife.  Plaintiffs sought to recover damages for injuries sustained when a platform upon which Urbina was kneeling collapsed at a construction site.  That platform had been installed by the drywall subcontractor, R&J Construction Corp. for its own use.  Plaintiffs brought claims against the owner of the premises, the lessee of the premises, and R&J.  The issues on appeal involved the reasonableness of the damages awarded to plaintiffs, and contractual indemnification between defendants. 

Continue Reading...

Construction Manager and Architect Not Liable for Construction Defects Where There is No Contractual Relationship with Plaintiff

Oates v. Larkin, 2007 WL 4442361 (Mass. Super. Ct. Dec. 5, 2007)

In this case, the Superior Court considered motions to dismiss brought by multiple defendants.  The case arose out of a large-scale condominium construction project.  Plaintiff was president of the association of unit owners and the defendants bringing motions to dismiss were the developer, its board of managers, the construction manager and the architect (who sought to join the motion to dismiss filed by the construction manager).  The developers’ and managers’ motions to dismiss were denied, provided that plaintiff complied with an order to amend the complaint.  The motion to dismiss by the construction manager was allowed in part, denied in part and the architect’s motion to join was allowed.
Continue Reading...

Materialman Rewarded for Detailed Lien Despite "Open Account"

BMC West Corp.  v. Horkley, 144 Idaho 890, 174 P.3d 399 (2007)

BMC West provided materials to contractor Davies for work on Horkley's commercial structure.  All sales were on an open account.  Davies did not fully pay BMC, so BMC filed liens “on the land on which the buildings were located, and on the buildings themselves.”  BMC then sued Horkley for payment and to foreclose the liens.  Horkley asserted the “open account defense,” which applies when a materialman “relies exclusively on the general credit of the purchaser, and does not look to the land, structure or building as additional security for the materials sold on credit.”  To avoid the defense and make the lien valid, the materials “must be furnished with special reference to their use in a particular building.”

Because BMC had tracked the materials sold to Davis for use on Horkley's building, it was not relying on Davies' general credit alone.  Since BMC was able to track the materials used to a specific project, the court granted summary judgment in favor of BMC.  The Idaho Supreme Court affirmed, including an award of attorney fees.
 

Tags:

No Summary Judgment for Contractors Relying on Preemption

Wysocki v. Kel-Tech Constr. Inc., 847 N.Y.S.2d 166 (N.Y. App. Div. 2007)

Here, the court denied the defendants’-contractors’ summary judgment motion to dismiss the breach of contract claims brought against them by plaintiffs-construction workers.  The court reasoned that the plaintiffs’ contractual rights would be independent of a collective bargaining agreement whether or not Labor Law § 220 was incorporated into the public works contracts at issue.  The court explained that Labor Law § 220 applies across the board, making its requirements non-negotiable.  Therefore, the collective bargaining agreement did not have any bearing on the public works contracts at issue in the case.

Second Department Grants Leave to Amend Answer to Plead Statute of Limitations Defense Under CPLR 214-c

Felice v. Am. A.W.S., Corp., 846 N.Y.S.2d 656 (N.Y. App. Div. 2007)

In this action, plaintiffs sought to recover for personal injuries and property damages arising out of defendant's renovation of plaintiffs’ residence.  Plaintiffs alleged that defendant had negligently performed the work, resulting in water leaks and the formation of mold.  Defendant sought leave to interpose an amended answer which included, inter alia, the affirmative defense of statute of limitations.  Defendant contended that the plaintiffs' causes of action sounded in negligence and thus were governed by a three-year statute of limitations. 

Continue Reading...

Appellate Court Accepts Measured Mile Method for Calculating Acceleration of Work Damages in Case of First Impression

James Corp. v. N. Allegheny Sch. Dist., 2007 WL 4208589 (Pa. Commw. Ct. Nov. 30, 2007)

In this case, the Commonwealth Court of Pennsylvania held that the trial court properly measured acceleration damages sustained by a general contractor under the “measured mile” theory of recovery.  In a multi-phased construction project entered into by the school district and James Corporation, the district delayed James’ performance by failing to obtain permits in a timely manner, by requiring extra work which interfered with the planned sequence of work, by relocating fencing and reconfiguring the erosion and sedimentation pond, and by requiring removal of asbestos (which was not in the contract).  Amidst the delay, the district abandoned the contract schedule, refused to consider the time impact on the contractor’s planned sequence, and then terminated the contractor after substantial completion.  The trial court awarded James damages for acceleration/compression of work, unpaid invoices, prevailing wages withheld, attorneys’ fees and expenses. Continue Reading...

General Contractor Liable to Subcontractor for Damages and Attorneys' Fees for Failure to Fully Compensate Subcontractor for Work on Change Orders

Am. Envtl. Contractors, Inc. v. Garber Constr. Co., Inc., 2007 WL 4358169 (Mass. Super. Ct. Nov. 26, 2007)

The Superior Court heard a jury-waived trial in which the plaintiff subcontractor sought damages from the defendant general contractor after an unexpected roof collapse created the need for substantial extra work on the project.  The general contractor and the project manager executed several change orders for extra work after the collapse.  The subcontractor claimed that it was not compensated for the full amount of extra work by the general contractor.  The general contractor claimed it was owed the money by the project manager and filed a third-party complaint. Continue Reading...

Material Supplier Deemed to Have Contracted with "Subcontractor" to Permit Claim Against "Miller Act" Bond

United States ex rel. E&H Steel Corp. v. C. Pyramid Enters., Inc., 509 F.3d 184 (3d Cir. 2007)

This litigation arose after a steel supplier on a U.S. government construction project asserted a claim against a payment bond issued by the general contractor (to which it had no contractual privity) pursuant to the Miller Act (40 U.S.C. § 3131).  Because the Miller Act limits the availability of such bond claims to either entities in contractual privity with the bond issuer (the GC) or those entities having contractual privity with a "subcontractor,” the key issue was whether the entity with which the supplier contracted was a “subcontractor.”  The District Court for the District of New Jersey, applying a number of a factors, determined that it was not a subcontractor and dismissed the bond claim.  

Continue Reading...

Fourth Department Rules on Labor Law Claims

Mulcaire v. Buffalo Structural Steel Constr. Corp., 846 N.Y.S.2d 838 (N.Y. App. Div. 2007)

In this case, a construction worker and a family member alleged Labor Law and common law negligence causes of action for injuries plaintiff sustained while installing floor decking in a building undergoing construction.  Plaintiff slipped and fell through an uncovered opening approximately 18 feet to the floor.  The trial court granted in part and denied in part plaintiffs' motion for summary judgment, and denied defendants' motion for summary judgment.  Defendants appealed.

Continue Reading...

Statute of Limitations Begins to Run When Subcontractor Completes All Work on Subcontract, Including Change Orders

N.B. Kenney Co., Inc. v. Nat’l Union Fire Ins. Co. of Pittsburgh, 876 N.E.2d 1175 (Mass. App. Ct. 2007)

In this case, the Massachusetts Appeals Court held that for the purposes of the statute of limitations, a subcontractor’s time to file suit begins to run at the completion of all work on a particular subcontract, including any change orders thereto. 

The defendant insurance company in this case moved for summary judgment on the basis that the plaintiff completed the change order giving rise to the complaint more than one year prior to filing suit and that the suit was therefor time-barred.  The court rejected this argument, holding that the subcontractor's work on other change orders pursuant to the same subcontract tolled the limitations period until all work on the subcontract was complete.  The court noted that continued work for the same owner or on the same location, but under a new and independent subcontract would not have tolled the limitations period.

Jury to Decide Whether Falling Debris was Foreseeable at Construction Site

Amerson v. Melito Constr. Corp., 845 N.Y.S.2d 457 (N.Y. App. Div. 2007)

In this case, the Second Department reversed a finding of summary judgment concerning an alleged violation of Labor Law § 241(6).  Plaintiff, a masonry subcontractor, was injured while performing his duties at the construction site when a concrete block fell on his head.  At the time he was injured, plaintiff was wearing a hard hart and had various pieces of equipment, including a chipping hammer, scraper, shovel and wheelbarrow, in his possession as needed to perform his work. Continue Reading...

General Contractor Not Entitled to Damages for Performing Subcontractor's Work, Where General Contractor Failed to Give Required Notice to Subcontractor

Rockwell Roofing, Inc. v. Jan Five Corp., 2007 WL 4248144 (Mass. Super. Ct. Nov. 15, 2007)

The Superior Court ruled on plaintiff’s motion for summary judgment on both its claim and defendant’s counterclaim.  The court allowed summary judgment in part and denied it in part.  Plaintiff subcontractor filed the action against defendant general contractor and its payment bond surety.  The defendant general contractor filed a counterclaim for breach of contract.  The subcontractor moved for summary judgment on the general contractor’s counterclaim, arguing that the general contractor failed to provide notice as required by the contract prior to performing work on the contract that was the responsibility of the subcontractor.  Summary judgment was granted, dismissing this portion of the general contractor’s counterclaim.
Continue Reading...

Chapter 558 Pre-suit ADR Process Does Not Apply to Construction Defect Claimant Who is Both Owner and Contractor

Specialty Eng’g Consultants, Inc. v. Hovostone Props. Fla., LLC, 968 So. 2d 680 (Fla. Dist. Ct. App. 2007)

This construction defect case involved a condominium project.  Defendant argued that the pre-suit alternative dispute resolution requirement in Chapter 558 of the Florida Statutes applied to the claimant, who was both the owner and the contractor of the project.  Chapter 558 requires that construction defect “claimants,” as defined therein, participate in a complex pre-suit ADR process, which includes various inspection and cure period requirements.  The definition of “claimant” in Chapter 558 specifically includes property owners, but specifically excludes contractors.  The court held that a construction defect claimant who is both the property owner and the contractor is not a “claimant” as defined in Chapter 558, and therefore the pre-suit ADR requirement did not apply.

Subcontractor Liability For Injuries Caused By Subcontractor's Equipment

Saccenti v. City of New York, 846 N.Y.S.2d 236 (N.Y. App. Div. 2007)

In this action based on Labor Law §§ 200 and 241(6) and common law negligence, the Second Department examined the lower court’s grant of summary judgment on all claims to defendant Hallen Construction, a subcontractor hired by a third-party defendant.  The claims involved injuries plaintiff sustained when he tripped over a spike Hallen had installed at the construction site in order to affix steel plates covering the trench it was excavating.
Continue Reading...

Default Judgment Overturned Due to Law Firm Error

Franco Belli Plumbing & Heating & Sons, Inc. v. Imperial Dev. & Constr. Corp., 845 N.Y.S.2d 446 (N.Y. App. Div. 2007)

In this case, the appellate court reversed a default judgment entered against defendant New York City School Construction Authority (“SCA”).  Plaintiff had claimed that Imperial Development & Construction Corp., the general contractor, owed over $253,000 to it as the sub-contractor for plumbing work on the project.  Imperial disputed the claim.  Pursuant to Public Authorities Law § 1735(6), plaintiff notified SCA, as the owner of the property where the disputed work took place, of its dispute with Imperial.  Also pursuant to that law, SCA was required to withhold the disputed amount of money from any payments it made to Imperial pursuant to the construction contract.  After plaintiff filed a note of issue, SCA disclosed that it had failed to withhold any money on plaintiff’s behalf.  Consequently, plaintiff moved to preclude SCA from introducing evidence regarding setoffs and back-charges with respect to its contract with Imperial on the basis that SCA had failed to respond to interrogatories seeking such information.  The Supreme Court granted this motion upon SCA’s default. Continue Reading...

Third Party Defendant's Summary Judgment Appeals Go Unheard

D’Angelo v. Builders Group, 845 N.Y.S.2d 814 (N.Y. App. Div. 2007)

This case involved an alleged violation of Labor Law § 240(1) and contractual indemnification.  Specifically, this decision involved an appeal brought by third-party plaintiff Builders Group from the lower court’s denial of its summary judgment motion seeking dismissal of the complaint and its cross-motion for summary judgment seeking contractual indemnification from third-party defendant Caruso Painting and Decorating Corp. Continue Reading...

Court Awards Liquidated Damages and Specific Performance in Breach of Construction Contract Case

Granite Broadway Dev. LLC v. 1711 LLC, 845 N.Y.S.2d 10 (N.Y. App. Div. 2007)

In this case, a contractor sued a property owner for breach of a construction contract.  After a bench trial, the court awarded the owner liquidated damages, certain offset damages, and specific performance.  The contractor appealed.

Continue Reading...

Statute of Repose Bars Negligence Claims After Passage of Six Years

Cusolito v. Care Free Homes, Inc., Civ. No. 05-00443, 2007 WL 5578208 (Mass. Super. Ct. Nov. 1, 2007)

On motions for summary judgment, the Superior Court held that the statute of repose barred all negligence-based claims filed by a homeowner against the defendant contractor who installed vinyl siding and the contractor’s president, and also barred the contractor’s third-party claims against a roofing contractor for contribution.  The court allowed the action to go forward on a claim by the homeowners premised on an express ten-year warranty by the vinyl-siding contractor.

Continue Reading...

Excessive Withholding Prompts Award of Interest, Attorney's Fees and Penalties under Pennsylvania's Prompt Payment Act

Imperial Excavating and Paving, LLC v. Rizzetto Constr. Mgmt., Inc., 935 A.2d 557 (Pa. Super. Ct. 2007)

Pennsylvania’s Prompt Payment Act (the “PPPA”) is intended to protect contractors and subcontractors by providing guidelines for prompt payment on construction projects.  Under the PPPA, every subcontractor working on a project subject to the PPPA is entitled to payment, according to the proportion of the subcontract completed, within 14 days of the date when the contractor receives a progress payment on the project.  73 PA.STAT. §507(c).  The contractor is, however, entitled to withhold such payment if it has a good faith claim for deficient performance.  73 PA.STAT. §511.  If a contractor unreasonably withholds payment to the subcontractor, the contractor can be assessed interest on the payment (73 PA.STAT. §509) plus a penalty of 1percent per month of the amount that was wrongfully withheld.  73 PA.STAT. §512.  The amount a contractor may withhold is proper if it “bears a reasonable relation to the value of any claim held in good faith.”  See Ruthrauff, Inc. v. Ravin, Inc., 914 A.2d 880 (Pa. Super. Ct. 2006).

The Imperial Excavating case involved the construction of two soccer fields located at a high school.  The grading subcontractor completed its work on the project and submitted an application for payment to the contractor.  The contractor submitted its own application for payment to the owner for the subcontractor’s work, certifying that the sub’s work was completed in accordance with the contract documents.  The owner paid the contractor’s application less retainage, and the contractor paid the subcontractor. Continue Reading...

Surety May Waive Right to Challenge Claim Against Payment Bond by Failing to Answer Notice of Claim, Even Where Claimant Did Not Submit Proof of Loss or Documentary Support

J.C. Gibson Plastering Co. v. XL Specialty Ins. Co., 521 F. Supp. 2d 1326 (M.D. Fla. 2007)

In this case, a subcontractor gave notice of a payment bond claim to a surety using a 14-page letter that set forth the factual and legal bases for the claim.  The subcontractor moved for summary judgment against the surety arguing that the surety waived its right to challenge the subcontractor’s claim because the surety failed to answer that notice of claim within 45 days, as required under the bond.  The surety argued in response that the subcontractor’s notice of claim was insufficient because the subcontractor disregarded the surety’s requests for:  (i) a “proof of loss,” and (ii) documentary support for the claim.  The surety also argued that, to the extent the court may consider the subcontractor’s notice sufficient, the surety’s requests for additional information satisfied the answer requirement under the bond because the requests indicated that the surety disputed the claim.
Continue Reading...

Contractor, But Not Owners of Contractor, Protected Under Maine's Insurance Guaranty Association Act

Belanger v. N. Am. Specialty Ins. Co., 504 F. 3d 147 (1st Cir. 2007)

In this case, North American Specialty Insurance Company, a surety, brought a suit against its principal contractor, Seacoast Crane Company and Seacoast’s owners (the “Belangers”) to recover monies paid out under a performance bond.  NAS had issued the performance bond on behalf of Seacoast to build a corporate headquarters project for DCC Development Corporation.  In the suit, initiated in the United States District Court for the District of Maine, NAS asserted claims for indemnification, breach of contract and specific performance based on a judgment that was entered against NAS and Seacoast, and against the Belangers for breach of contract in connection with the DCC project. Continue Reading...

Undermining Competitive Bidding Process through Collusion Violates Massachusetts Consumer Protection Act

Prof’l Servs. Group v. Town of Rockland, 515 F. Supp. 2d 179 (D. Mass. 2007)

In this case, the Federal District Court for the District of Massachusetts issued a decision concerning the subversion of the public procurement process by a bidder.  The defendant-contractor colluded with a public official of the plaintiff-town to ensure that it would be the only bidder and would thereby receive the bid at an artificially high price.  The court held that this collusion violated the Massachusetts Consumer Protection Act (M.G.L. c. 93A), and that the town was entitled to double damages pursuant to that that statute because the contractor’s violations were knowing and willful.  The contractor attempted to escape liability by arguing that the employee who was responsible for the bidding and collusion was a rogue employee.  The court rejected this argument and found that the contractor’s employee was acting within the scope of his employment and therefore the contractor was liable by the doctrine of respondeat superior. Continue Reading...

Statute of Repose Begins to Run on Negligence and Implied Warranty Claims when Building Occupants are First Issued Certificate of Occupancy

Great N. Ins. Co. v. Architectural Env'ts, Inc., 514 F. Supp. 2d 139 (D. Mass. 2007)

On a motion for summary judgment, the Federal District Court for the District of Massachusetts held that for the purposes of the statute of repose, the limitation period began running when the temporary certificate of occupancy was issued on the building in question. 

In this case, a fire occurred at a commercial property as a result of an electrical malfunction.  The occupant’s insurer sued the mechanical and electrical contractor responsible for design and renovation of the building.  The court held that the statute of repose began to run on the date that the temporary certificate of occupancy was issued on the building, and not at the later date when the permanent certificate was issued.  Thus, the plaintiff’s claims for negligence and implied warranties were time-barred by the six-year statute of repose.  Express warranties, however, were not subject to the statute of repose and those claims survived summary judgment.

Oregon Federal Court Remands Contractor Garnishment Action to State Court

Triad Mech. v. Coatings Unlimited, Inc., 2007 WL 2713842 (D. Or. Sept. 12, 2007)

A general contractor successfully obtained a judgment against a subcontractor for breach of contract and negligence arising from a construction project.  The general contractor then sought a garnishment action against one of the subcontractor’s insurers to collect the judgment, which was filed in Oregon state court.  The general contractor was an additional insured under the subcontractor’s comprehensive general liability insurance.  The insurer removed the action to federal court and the general contractor sought remand to state court.  The district court remanded the action to state court.

Continue Reading...
Tags:

Unintended Construction Defects May Constitute an "Accident" or "Occurrence" Under Commercial General Liability Policy

Lamar Homes, Inc. v. Mid-Continent Cas. Co., 242 S.W.3d 1 (Tex. 2007)

In this landmark decision, the Texas Supreme Court ruled that commercial general liability policies provide a duty to defend claims for property damage caused by an insured contractor’s defective construction.  Resolving a split of authority on certified questions from the Fifth Circuit, the court ruled that unintended construction defects may constitute an “accident” or “occurrence” within the meaning of a commercial general liability policy.  It also ruled that the resulting damage to or loss of use of the building may constitute “property damage” sufficient to trigger the insurer’s duty to defend.  The court also held that the CGL policy made no distinction between tort and contract damages, rejecting the insurer’s economic loss rule defense.

Continue Reading...
Tags:

Property Owner's Claims Against Professional Engineer Reinstated Where Contractor Placed Water Line Outside of Utility Easement

Merlini v. Gallitzin Water Auth., 934 A. 2d 100 (Pa. Super. Ct. 2007)

In this case, the Superior Court of Pennsylvania held that a professional engineer can be either “ordinarily negligent” or “professionally negligent” in the performance of his consulting engineering tasks, or both.  He can be accountable in damages for mere negligence under common law theories of trespass, even if a plaintiff is not suing him for professional negligence.

This odd outcome is the result of an engineer directing a contractor to install a water line, without right-of-way, easement or permission, in the wrong place on the property owner’s property, that is, in a location outside of the recorded easement.  When the property owner filed a complaint in the court, but did not file the technically required certificate of merit of professional negligence required by the Pennsylvania Rules of Court, the property owner’s complaint was dismissed.  The property owner appealed, and the Superior Court had to determine whether the property owner’s complaint was asserting ordinary negligence or “professional negligence.”
Continue Reading...

Findings of Arbitrator Will Not Be Overturned in Absence of Fraud

Site, Inc. v. Peabody Constr. Co., Inc., 2007 WL 2458482 (Mass. App. Ct. Aug. 30, 2007) (Unpublished)

In this case, the Appeals Court affirmed the Superior Court’s denial of plaintiffs’ motion to vacate an arbitration award.  The defendant general contractor, Peabody Construction Company, refused to pay the plaintiff subcontractor, Site, Inc. on a subcontract after terminating the subcontractor prior to completion of the job.  The case went to arbitration.  After considering extensive evidence and testimony, the arbitrator found that the general contractor’s failure to make timely payment was a material breach of the subcontract.  Although the arbitrator found that general contractor’s material breach of the subcontract excused any subsequent failure by the subcontractor to perform its obligations under the subcontract, the arbitrator found that the subcontractor was not entitled to payment for the work it performed because the subcontractor “had not completely [and satisfactorily] performed all of its obligations under the subcontract.” Continue Reading...

Subcontractor Agreements Are "Residential Construction Contracts" Under New Jersey Construction Lien Law

In re Kara Homes, Inc., 374 B.R. 542 (Bankr. D.N.J. 2007)

On an issue never before addressed in a published opinion, a U.S. Bankruptcy Court decided an issue critical to the New Jersey Lien Law.  A major New Jersey based residential home building group (the “Debtors”), owning several large single-family home development projects, entered numerous agreements with various subcontractors who provided goods and services on the projects.  When the Debtors failed to pay, the subcontractors took steps to protect their rights under the New Jersey Construction Lien Law.  However, most of the Debtors initiated Chapter 11 bankruptcy proceedings before the subcontractors could fully complete all of the Lien Law's requirements.  The Debtors then filed adversary proceedings to determine the extent, validity, and priority of any liens.

 

Continue Reading...

Improperly Awarded Public Contract Can Survive Where Bid Process Was Fair and Re-Bid Would Be Inequitable to Public Entity and Taxpayers

Alaska Servs., Inc. v. County of Morris, 2007 WL 2385941 (N.J. Super. Ct. App. Div. Aug. 23, 2007)

In this case, a county solicited bids for laundry services for a county-run nursing care facility pursuant to New Jersey’s Local Public Contracts Law (“LPCL”) (N.J.S.A. 40A:11-1, et seq.).  The county refused to award the contract to the lowest bidder, finding that the bid was “materially non-responsive," and because the services were such that the county could utilize the LPCL’s “competitive contracting” provision (an exception for certain “special” goods and services permitting a public entity to consider additional factors beyond the “lowest responsible bidder” standards set by the LPCL).  The county awarded the contract to another bidder.

Continue Reading...

General Contractor Not Required to Provide Insurance Covering Project Owner's Own Negligence Absent Clear Contract Language Requiring Such Coverage

Gale v. New Jersey Iron, Inc., 2007 WL 2385948 (N.J. Super. Ct. App. Div. Aug. 23, 2007)

This case arose after an employee of a sub-subcontractor sued the project owner, the general contractor (“GC”) and the subcontractor for negligence over personal injuries he sustained after falling from a steel beam at the construction site.  All issues settled except for the owner’s cross-claim against the GC alleging that the GC breached its contract when it failed to obtain insurance coverage that protected the owner from its own negligence.

The Appellate Division affirmed the trial court’s dismissal of the claim.  Initially, the court determined that the “insurance” section of the contract did not specifically require such insurance and was more consistent with the industry standard requiring a GC to provide insurance to indemnify an Owner against acts of negligence by the GC or a subcontractor.  Moreover, the "indemnity” section of the contract merely required the GC to indemnify the owner only to the extent caused by the GC, a subcontractor or anyone employed by them.

Court Upholds City's Product Specification for Construction Project, but Notes that City Does Not Have Unfettered Discretion In Prohibiting Products

Advanced Drainage Sys., Inc. v. City of Portland, 214 Or. App 534, 166 P.3d 580 (2007)

A pipe manufacturer sought a declaratory judgment that the city had violated its state and federal constitutional rights to equal treatment when it rejected the use of a certain type of pipe for a city contract.  The city counterclaimed, asserting that it had complete discretion to choose products for its construction projects.  The trial court agreed with the city.  The court of appeals affirmed, but with a modification.

The city tried to argue that the manufacturer was not a citizen under the Oregon constitution and therefore lacked standing.  The appellate court left that issue for another day, deciding that it would determine standing as an issue of justiciability and not as a matter of constitutional interpretation.  The appellate court then determined that the city’s ordinances which prohibited certain types of pipe materials but not others passed any applicable tests of rationality based upon asserted claims regarding safety and maintenance.  However, the appellate court also determined that, contrary to the city’s argument, the city did not have unfettered discretion in prohibiting certain types of products and hence manufacturers.  Thus, the city could not prohibit products made by “Catholics or Norwegians," for example.

Tags:

General Contractor Bears Burden of Disproving Claim for Employer Contributions by Labor Union Under Collective Bargaining Agreement

Kane Builders, Inc. v. S. New Jersey Bldg. Laborers Dist. Council, LIUNA, 2007 WL 2416470 (D.N.J. Aug. 21, 2007)

In this case, a labor union brought various claims against a general contractor (“GC”) stemming from a collective bargaining agreement (“CBA”) entered between the Union and the GC.  Briefly stated, the union asserted a multi-million dollar claim for unpaid employer contributions that the GC would have been obligated to pay, had it not violated the CBA by not using union laborers on over 100 “covered projects” in New Jersey.  Relying on ERISA’s record keeping provision (29 U.S.C. § 1145), the union argued that the GC bore the burden of proving which hours worked were not subject to contribution. 

The court, following 11th Circuit precedent, adopted the burden-shifting approach.  It determined that the union had satisfied its initial burden of setting forth sufficient evidence concerning the amount and extent of work performed through an expert auditor’s report.  The court ruled that, at that point, the burden of proof shifted to the GC to disprove, or raise an issue of fact, regarding the extent of work performed on covered projects and/or whether covered employees performed the work.  Because the GC was unable to produce any records to disprove the union’s claim, the court entered partial summary judgment on the issue of damages.

Courts Apply Heightened Pleading Standards to Fraud Claims in Adversary Proceeding

In re Andrew Velez Constr., Inc., 373 B.R. 262 (Bankr. S.D.N.Y. 2007)

This adversary proceeding was brought by Andrew Velez Construction, Inc. (“Velez”), a general contractor on a major construction project for Con Edison Company of New York, Inc. (“Con Edison”), against Con Edison.  After substantial cost overruns, delays and changes in the scope of work, the parties each claimed that the other committed pre-petition defaults under their contract.  The parties asserted numerous causes of action, including claims for: fraudulent transfers, turnovers, declaratory relief, fraud, fraudulent inducement, quantum meruit, unjust enrichment, trust fund violations, and defamation.  Because the court was presented with Con Edison’s motion to dismiss, this decision examined the pleading standards for each claim.

Continue Reading...

Court Favors Arbitration in Disputes Between Contractor and Subcontractor

Actus Lend Lease LLC v. Integrated Bldg. Res. Dev. LLC, 2007 WL 2362389 (N.D.N.Y. Aug. 14, 2007)

Here, defendant moved to dismiss the action for breach of its subcontract with plaintiff-contractor on the basis that the action was subject to binding arbitration.  According to the subcontract, a dispute between the parties must be resolved by mandatory arbitration when the dispute (1) arises in connection with the subcontract and either party elects, by written notice, to submit the matter to binding arbitration; or (2) involves the correlative rights and duties of the owner.  The subcontract also provided that a party must provide written notice to elect binding arbitration.

In support of its motion, defendant submitted a notice of motion and an affirmation with exhibits; however, it did not submit a memorandum of law to set forth its legal arguments.  The court held, therefore, that factual disputes existed as to whether the alleged dispute was subject to arbitration under the terms of the agreement.  However, the court granted defendant leave to renew its motion to dismiss upon submission of the proper papers, reasoning that there is a strong public policy in favor of arbitration.

Scope of Arbitration Agreement in Home Warranty to be Determined by Arbitrator, Not Court

Mercedes Homes, Inc. v. Colon, 966 So.2d 10 (Fla. Dist. Ct. App. 2007)

In this case, an individual entered into an agreement with a contractor for construction of a new home, which included a provision requiring the contractor to install sod.  When the home buyer fell in his yard eleven days after closing, he brought a personal injury claim against the contractor claiming it had installed the sod negligently.  The contractor moved to compel arbitration of the personal injury claim, based on the arbitration agreement contained in the home warranty purchased by the home buyer.  In response, the buyer argued that he was not required to arbitrate his personal injury claim because negligence claims were expressly excluded from the home warranty.

Continue Reading...

Contractor Not Required to Provide Pre-Suit Notice, May Plead Both Negligent Construction and Breach of Contract

Centex Homes v. Mr. Stucco, Inc., 2007 WL 2264622 (M.D. Fla. Aug. 6, 2007)

In this case, a general contractor brought suit against several subcontractors for breach of contract and negligent construction of residences in the general contractor's development.  In response, the subcontractors moved to dismiss the action on the grounds that the contractor had failed to provide notice prior to filing the action as required by section 558.004 of the Florida Statutes.  The subcontractors also moved to dismiss the negligence claim on the grounds that the contractor had not alleged any tort injury separate from the breach of contract claim in order to survive the economic loss rule.

Continue Reading...

Insurer Has Duty to Defend General Contractor for Injuries Arising Out of Subcontractor's Work Where General Contractor is Named as Additional Insured on Subcontractor's Policy

Parker v. John Moriarty & Assocs., Inc., 2007 WL 2429719 (Mass. Super. Ct. July 29, 2007)

This case arose from personal injuries suffered by the plaintiff while working at a construction site in Brighton, Massachusetts.  The general contractor of the construction project subcontracted some aspects of the project; plaintiff was an employee of the subcontractor.  The plaintiff filed a complaint, asserting a negligence claim against the general contractor for negligently failing to provide a safe workplace and the general contractor settled.  By third-party complaint, the general contractor brought claims against the subcontractor and the subcontractor’s insurer for indemnification, contribution, and breach of contract for failure to provide insurance.  The insurer moved for summary judgment on all claims against it, arguing that the insurance policy did not provide coverage on the claims.  The insurer argued that it did not owe a duty to defend the claims and did not have a duty to indemnify because the general contractor was not covered for the claims under the additional insured endorsement and such claims were excluded from coverage under the cross-suits provision.  The general contractor opposed and filed a cross-motion for summary judgment, asserting that, as a matter of law, the policy provided coverage in that the insurer had a duty to defend and to indemnify for the settlement of the claims.  The subcontractor also moved for summary judgment in its favor on the breach of contract claim for failure to provide insurance, arguing that it had named the general contractor as an additional insured on the policy. Continue Reading...

Insurer Not Entitled to Summary Judgment on Breach of Performance Bond Claim

Klewin Bldg. Co. v. Heritage Plumbing & Heating, Inc., 840 N.Y.S.2d 144 (N.Y. App. Div. 2007)

In this case, plaintiff was the construction manager for a building project and had entered into a subcontract with defendant Heritage Plumbing & Heating pursuant to which Heritage was required to supply plumbing materials and services for the project.  Defendant Hartford Fire Insurance Company provided a performance bond to Heritage for the benefit of Klewin.   Hartford's obligations to Klewin under the bond would only arise upon certain conditions, including, among other things, Klewin's declaration that Heritage had defaulted and a termination of Heritage's right to complete the subcontract.

Continue Reading...

Court of Claims Ruling Upheld - Contractor Entitled to Reimbursement from Government Under Unit Contract

Harrison & Burrowes Bridge Constructors, Inc. v. New York, 839 N.Y.S.2d 854 (N.Y. App. Div. 2007)

The claimant filed suit in the Court of Claims seeking additional compensation for its rehabilitation and resurfacing of eight bridges under a unit-price contract with the State of New York.  The state offered several reasons for its refusal to pay the claimant for labor and materials supplied under the contract.

First, the contract required the state to pay the claimant for the total number of markers installed, including any markers damaged by traffic.  The state refused to pay for an additional 1,478 replacement markers installed by the claimant, arguing that the bid proposal, upon which the contract was based, only covered the installation of 868 markers.  Affirming the Court of Claims, the appellate court found that the state should pay for the additional 1,478 replacement markers.  Although the contract (which required the claimant to replace damaged markers) did not specify who would be obligated to pay for those markers, the court reasoned that the contract did not require the claimant to include the cost of replacing markers in its bid.

Continue Reading...

Economic Loss Rule Remains Alive and Well in Texas

Pugh v. Gen. Terrazzo Supplies, Inc., 243 S.W.3d 84 (Tex. Ct. App. 2007), petition for review filed (Mar. 24, 2008)

In this case, the court affirmed a take-nothing summary judgment in favor of a materials supplier based on the economic loss rule.  Pugh arose out of a residential construction project involving an exterior insulated finishing system (“EIFS”).  After discovering alleged water damage to their home’s wood frame and interior wood flooring, the homeowners sued the masonry subcontractor and veneer supplier for negligence, “product liability (marketing defect),” and breach of the “implied warranties of good and workmanlike service and habitability.” 

In a motion for summary judgment, the material supplier argued that the economic loss rule barred the homeowners’ claims for negligence and strict liability.

Continue Reading...
Tags:

Massachusetts Building Code Does Not Render Either Engineer or Architect Liable for Unsafe Working Conditions on Owner's Site

Garcia v. Federics, 2007 WL 2367672 (Mass. Super. Ct. July 9, 2007)

In this case, the Superior Court granted a motion for summary judgment brought by the architect and engineer of a project on claims asserted by a construction worker injured on the job.  As grounds for its ruling, the court found that neither the contract between the owner and the construction company nor the contract for architect’s services assigned responsibility to the architect or engineer for safety issues on the project.  Thus, the court found that the architect and engineer did not have a contractual duty to protect the worker against unsafe working conditions. 

In reaching its decision, the court rejected plaintiff’s argument that the Massachusetts Building Code created a duty for the architect and engineer to control safety conditions.  Specifically, the court noted that the Massachusetts Building Code places the responsibility for the conditions of the building on the owner of the building rather than the architect or engineer.  Plaintiff’s additional claims also failed because he could not demonstrate a reasonable expectation of proving that the architect and the engineer had a duty of care to the worker.  The cross-claims by the owner failed because the architect and the engineer were not directly liable to the worker.

General Contractor Has No Indemnification Claim Against Subcontractor Where Claims Arise Out of Contractor's Own Failure to Supervise

Fireman’s Fund Ins. Co. v. Falco Constr. Corp., 493 F. Supp. 2d 143 (D. Mass. 2007)

A property insurer, Fireman’s Fund Insurance Company, asserted claims against a general contractor and subcontractor after an insured home sustained fire damage.  The general contractor had performed extensive renovations on the home, and the subcontractor had constructed a masonry fireplace at the home.  In Counts I and II, the insurer sought recovery from the subcontractor for improperly installing the fireplace on theories of negligence and breach of contract.  In Counts III and IV, the insurer brought the same claims against the general contractor for failing to supervise.  The general contractor subsequently filed a cross-claim for indemnification against the subcontractor. Continue Reading...

Cancelled LLC Can Be Sued, But Cannot Sue

Chadwick Farms Owners Assoc. v. FHC, LLC, 139 Wash. App. 300, 160 P.3d 1061 (2007)

This case presents a similar set of facts to Maple Court.  Condominium developer FHC, LLC was administratively dissolved on March 24, 2003.  On August 18, 2004, Chadwick Farms Homeowner’s Association filed suit against FHC, alleging construction defects.  Seven months later, on March 24, 2005, FHC was administratively cancelled because it failed to reinstate during the two-year dissolution period.  Two months after cancellation, FHC filed third party claims against its subcontractors, and in August 2005 moved for summary judgment against Chadwick on the ground that it was no longer a legal entity.
Continue Reading...

Developer and Construction Manager Lose Pending Claims

Maple Court Seattle Condo. Assoc. v. Roosevelt, LLC 139 Wash. App. 257, 160 P.3d 1068 (2007)

In June 2007, Division One of the Court of Appeals rendered its decisions in three cases involving the issue of a dissolved limited liability company's standing to maintain claims.  Maple Court illustrates the adverse impact that administrative dissolution can have on the pending claims of a developer and general contractor.

On September 23, 2002, condominium developer Roosevelt, LLC allowed itself to be administratively dissolved by the Secretary of State.  Fifteen months later, Roosevelt was sued by the condominium homeowners' association.  In response, Roosevelt filed third party complaints against its construction manager and subcontractors.  During the pending litigation, on September 23, 2004, Roosevelt was administratively "cancelled" pursuant to RCW 25.15.270(6) because it did not reinstate itself following the prior administrative dissolution.
Continue Reading...

Government Agency May Compel Production of Documents in Specific Format Through Subpoena Duces Tecum

Nat’l Labor Relations Bd. v. Champagne Drywall, Inc., 502 F. Supp. 2d 179 (D. Mass. 2007)

Under the National Labor Relations Act, the National Labor Relations Board moved for an order from the court to enforce two subpoenas duces tecum served on Champagne Drywall as part of the NLRB’s investigation of Champagne's alleged practice of refusing to consider and hire qualified job applicants based on their union affiliation.  Champagne objected because even though the data sought existed within the organization, Champagne did not possess the information in the format sought by the NLRB – namely, as a list. Continue Reading...

General Contractor May Recover from Subcontractor Without Joining Owner as Party

Floor Express, Inc. v. Daly, 138 Wash. App. 750, 158 P.3d 619 (2007)

In this case, a subcontractor sued a general contractor for failing to make payments on the parties’ contract.  The general contractor asserted a counterclaim against the subcontractor for the cost of removing and replacing the subcontractor’s work.  On the first day of trial, the subcontractor moved to dismiss the counterclaim, arguing that the project owner was a necessary party and that the general contractor had no standing to sue the subcontractor because the alleged defective work injured only the owner.  The trial court granted the motion, but Division Two reversed.

The Court of Appeals noted that, where a subcontractor breaches its agreement with a general contractor by failing to perform the work pursuant to the parties’ agreement, the general contractor has legal exposure to the owner.  The court held that the owner was not a necessary party to the litigation under Civil Rule 19 because the general contractor’s claims were based on the subcontract, to which the owner was not a party.  The court also held it could afford complete relief to the general contractor, and that the owner’s absence did not impede any of the owner’s interests.  Accordingly, the general contractor’s claim against the subcontractor should have been allowed to proceed.

Winning Race to Courthouse Does Not Win ERISA Preemption

Bd. of Trustees of Cement Masons & Plasterers Health & Welfare Trust v. GBC Northwest, LLC, 2007 WL 1306545 (W.D. Wash. May 3, 2007), reconsid’n denied, 2007 WL 1521220 (W.D. Wash. May 22, 2007)

A split of authority exists between Washington state courts and federal courts regarding whether an employee benefit trust fund can use state lien laws to recover unpaid employee benefit contribution payments.  In 2000, the Washington Supreme Court held that ERISA preempted the state public works lien law.  Int'l Bd. of Elec. Workers v. Trig Elec. Contr. Co., 142 Wash.2d 431, 13 P.3d 622 (2000).  Two years later, however, Judge Coughenour of the U.S. District Court for the Western District of Washington noted that federal law, as determined by federal courts, governs questions of ERISA preemption, and that ERISA does not preempt Washington’s public works lien laws.  Ironworkers Dist. Council of the Pacific Northwest v. George Sollit Corp., M.A., 2002 WL 31545972 (W.D. Wash. Sept. 4, 2002).

Continue Reading...

Agreement to Arbitrate Prejudices Insurers

MacLean Townhomes, LLC v. Am. States Ins. Co., 138 Wash. App. 186, 156 P.3d 278 (2007)

In this case, a homeowners association informed its developer about certain construction defects attributable to the building’s siding subcontractor.  The developer was named as an additional insured on the siding subcontractor’s commercial general liability insurance policy.  However, the developer failed to give the insurer notice of the defects and potential claim.  The developer further agreed (again without notice to the insurer) to enter into binding arbitration with the homeowners association.

Division One affirmed summary judgment in favor of the insurer, holding that the developer’s failure to give notice was a violation of the insurance policy, prejudiced the insurer, and was therefore fatal to the developer's claim.  Acknowledging that prejudice is normally a question of fact, the court held that the developer’s agreement to binding arbitration deprived the insurer of full judicial review of the matter.  This inability to seek review of a decision, for example, in the case of an error of law, necessarily prejudiced the insurer and excused the insurer of its duty to defend the developer. 

Economic Loss Rule Does Not Bar Owner's Negligence Claim Against Subcontractor

Lord v. Customized Consulting Specialty, Inc., 182 N.C. App. 635, 643 S.E.2d 28 (Ct. App. 2007)

In this case, homeowners sued their contractor regarding defective trusses installed in their home, and also brought a negligence claim directly against the subcontractor which supplied the trusses.  A jury awarded no damages against the contractor, but did award damages against the subcontractor.  The subcontractor argued on appeal that the economic loss rule barred the homeowners’ claim.  The North Carolina Court of Appeals affirmed the jury verdict against the subcontractor, holding that the economic loss rule does not bar a negligence claim in the absence of a contract.

Continue Reading...

Contractors Have Lien Rights on Improvements Built on Public Property

Haselwood v. Bremerton Ice Arena, Inc., 137 Wn. App. 872, 155 P.3d 952 (2007)

In this case, Division Two of the Washington Court of Appeals considered whether and to what extent a contractor has lien rights on a private building constructed on public property.  The City of Bremerton entered into a concession agreement with Bremerton Ice Arena, Inc. (“BIA”), under which BIA would construct an ice arena on city property and would own and operate the arena for a specified period of time.  After the expiration of that period of time, ownership of the arena improvements would transfer to the city. 

The excavation and drainage subcontractor on the project claimed it was unpaid for a portion of its work, and filed a lien the project.

Continue Reading...

Lenders Can Pull Financing if Borrower Cannot Show It Is Ready, Willing and Able to Perform All Conditions Required for Loan

Boise Tower Assocs. LLC v. Wash. Capital Joint Master Trust, 2007 WL 1035158 (D. Idaho Apr. 2, 2007)

In this case, the federal court sitting in Boise applied Washington law in delivering a win for a lender who refused to lend to the plaintiff developer.  The lender agreed to provide financing, but only if four conditions precedent were met, including an agreement to use union labor.  The developer agreed, but later took steps to have his contractor use non-union labor.  The lender refused to loan, prompting a lawsuit by the developer.  The court held that the lender was entitled to refuse because the developer had not demonstrated that it was willing and able to perform the conditions precedent.  A party, here the developer, that claims to have been damaged by a repudiation must show that it was ready, willing and able to perform its obligations under the contract before the repudiation, and that it would have rendered the agreed performance if the defendant had not repudiated.  The developer could not do so here, so the court excused the lender from making the loan.


Tags:

State Not Liable to Workers Who Also Recovered Under Workers' Compensation System

Fuhriman v. Idaho Dept. of Transp., 143 Idaho 800, 153 P.3d 480 (2007)

Idaho law provides that workers' compensation benefits are the exclusive remedy for workplace injuries.  Idaho Code §72-223, however, contains an exception to that "exclusive remedy."  The exception allows a finding of liability against a third party, even where the injured employee has received worker's compensation benefits, if the third party is legally liable for damages.  This exception to the exclusive remedy rule does not apply, however, to employers described in §72-216, which includes third party that has expressly or impliedly hired or contracted the services of another, including contractors and subcontractors, and the third party is liable to pay workers’ compensation benefits if the direct employer, the contractor or subcontractor, does not.

In a February 2007 opinion, the Idaho Supreme Court held that the Idaho Department of Transportation was not subject to the exception (that is, it was protected by the exclusive remedy rule).  The State was using workers employed by a contractor.  Those workers were killed on the job.  Their families received workers' compensation benefits and sued the State.  The Court rejected the claims, however, because the State would have been liable for the worker's compensation benefits if the contractor/employer failed to pay those benefits.  The exception therefore did not apply.

Tags:

Be Very Careful When Entering into Settlement Agreements

Ragnar Benson, Inc. v. Hempfield Township Mun. Auth., 916 A.2d 1183 (Pa. Super. Ct. 2007)

The Pennsylvania Superior Court untied the knottiest of two settlement agreements in this case.  Under separate written agreements, Kirby Electric contracted with the Municipal Authority to do its electrical construction, while Ragnar Benson contracted to perform general construction on the Authority’s water pollution control plant.  Each filed a lawsuit against the Municipal Authority, asserting breach of contract, and the Municipal Authority counterclaimed, and cross-claimed accordingly.  Kirby and the Municipal Authority agreed to settle their claims and counterclaims, with the provision that Kirby and Ragnar would continue in litigation and that settlement payments would be calculated based upon the outcome of the two contractors’ litigated dispute.
Continue Reading...

Contract Specifications Defense Applies to Both Private and Public Contractors

Craig Johnson Constr., L.L.C. v. Floyd Town Architects, P.A., 142 Idaho 797, 134 P.3d 648 (2006)

Town entered into a contract with Dean to prepare plans for condominiums in Ketchum.  Once Dean received the plans, Dean contracted with Johnson to build the condominiums according to Town’s plans.  The condominiums were built in two phases.  In Phase one Johnson deviated from the plans, but did not do so in building phase two.  The first winter the condominiums were completed, ice dams formed on the roofs of individual units in both phases of construction.  All three parties then brought actions against each other for breach of contract, negligence and indemnification. 

At trial, the jury found Johnson to be 90 percent at fault and Town only 10 percent at fault.  The court held that “a public or private contractor following plans and specifications prepared by another party is not liable in negligence where defects in the plans and specifications cause injuries, so long as the contractor should not have reasonably known about the defects.”  The court affirmed the jury’s verdict since there was sufficient evidence in the record to show that Johnson was negligent and failed to follow Town’s plans. 

Tags:

Owner Who Pays Contractor After Receiving Subcontractor's Lien Notice Becomes Personally Liable to Subcontractor, Even Though Owner Retains More than Lien Amount

O & M Indus. v. Smith Eng’g Co., 360 N.C. 263, 624 S.E.2d 345 (2006)

In this case, the subcontractor served a notice of claim of lien on funds owed to it by the contractor.  The owner paid the contractor after the subcontractor served notice, but also retained funds in excess of the subcontractor’s lien.  The subcontractor sued when neither the contractor nor the owner paid it.  The subcontractor moved for summary judgment, alleging that the owner was personally liable because it paid the contractor after the subcontractor served notice.  The owner also moved for summary judgment.  The trial court granted the subcontractor’s motion for summary judgment and denied the owner’s.  The Court of Appeals reversed, but the North Carolina Supreme Court reversed the Court of Appeals, holding, among other things, that the Court of Appeals failed to properly apply the applicable lien statutes, and that the owner’s retention of funds exceeding the lien did not relieve the owner of personal liability.

Continue Reading...

New York Public Policy Against Pay-If-Paid Provision Does Not Apply to Contracts Governed by Jurisdictions That Do Not Share That Policy

Welsbach Elec. Corp. v. MasTec N. Am., Inc., 7 N.Y.3d 624 (2006)

Welsbach involved a general contractor engaged to construct a telecommunications network in New York.  The agreement between the general contractor and sub-contractor included a pay-if-paid clause and a Florida choice of law provision.  The New York Court of Appeals decided that New York’s public policy against pay-if-paid contract provisions was not so fundamental that it would override the parties’ choice of law.

The significance of this ruling is that it is now possible for a subcontractor to find that its lien rights are imported if it does business under the law of a non-West-Fair state.

California Business and Professions Code § 7031(a) Bars Recovery for Unlicensed Contract Work Even if Contractor Receives a License Prior to Completion; Contractor Must Have License Before Starting Work

MW Erectors, Inc. v. Niederhauser Ornamental & Metal Works Co., Inc., 36 Cal. 4th 412 (2005)

In this case, the California Supreme Court expanded on the body of licensing law set forth in Hydrotech Sys. Ltd. v. Oasis Water Park, 52 Cal. 3d 998 (1991).

In MW Erectors, subcontractor Niederhauser Ornamental & Metal Works Company was hired to perform specialized metal work on a project.  Niederhauser awarded two contracts to MW Erectors, one for “structural” steel work and one for “ornamental” steel work.  MW Erectors began work on the structural contract on December 3, 1999, but did not receive a steel contractor’s license until December 21, 1999.  MW Erectors began work on the ornamental contract in early January.  MW Erectors subsequently sued Niederhauser and its payment bond surety for amounts due on both contracts.  The trial court granted summary judgment in favor of Niederhauser.  The court of appeals reversed, and held that MW Erectors was entitled to prove amounts due for its work on the structural contract after the license was issued.
Continue Reading...

Court Finds Contractor Has No Claim for Implied Indemnity or for Contribution Against Subcontractors

Kaleel Builders, Inc. v. Ashby, 161 N.C. App. 34, 587 S.E.2d 470 (2003)

In this case, homeowners hired an architect to design their residence, and also hired Kaleel Builders, Inc., as contractor to construct the residence.  Kaleel in turn hired several subcontractors. In the fall of 1996, the homeowners halted construction, and filed an arbitration demand against Kaleel alleging defective construction, including the work by the subcontractors and the design/supervision of the architect.  While the arbitration was pending, Kaleel filed a complaint seeking indemnification and/or contribution against the subcontractors and architect in July of 2001.  The trial court dismissed the claims against the subcontractors.  The claims for breach of warranty and breach of contract were dismissed on statute of limitations grounds, and the claims for negligence, indemnity, and contribution were dismissed for failure to state a claim.  The trial court also granted summary judgment for the architect.  The North Carolina Court of Appeals affirmed the trial court’s decision on all claims.

Continue Reading...

Statute Adopting Several Liability in Tort Actions Does Not Apply to Contractual Indemnification Actions

Moen Co. v. Island Steel, 128 Wash. 2d 745, 912 P.2d 472 (1996)

Here, a general contractor, Moen, who had settled with an employee of the subcontractor, Island, injured in an accident at a construction worksite sought contractual indemnification from the subcontractor pursuant to RCW 4.24.115.  The principle issues in this case were:  (1) whether the contractor could enforce its indemnification agreement in which the subcontractor waived its employer immunity under RCW Title 51 and which purports to shift liability to the extent of the subcontractor’s negligence (despite RCW 4.22.070 which adopts several liability in tort cases), and (2) to what extent the subcontractor was liable to contractor, if at all. Continue Reading...

Existence of "Good Faith Dispute" Allows Contractor to Withhold Payments and Avoid Prompt Payment Penalties

Alpha Mech., Heating & Air Conditioning, Inc. v. Travelers Cas. & Sur. Co. of Am., 133 Cal. App. 4th 1319 (2005)

In this case, subcontractor Alpha Mechanical, Heating & Air Conditioning sued general contractor RAS Builders and payment bond issuer Travelers after RAS withheld a final payment on the grounds that Alpha Mechanical had damaged other trades’ work.  At trial, Alpha Mechanical argued that RAS failed to comply with California prompt payment statutes because RAS failed to give timely notice of any good faith dispute.  Travelers countered that the existence of a good faith dispute precluded the award of prompt payment penalties, and that RAS offered evidence that Alpha Mechanical had been notified of every backcharge.  The trial court awarded Alpha Mechanical the principal amount owed, penalty interest, prejudgment interest and attorneys fees and costs.
Continue Reading...

New York Law Allows Subcontractors' Assignees to Recover From Sureties

Quantum Corporate Funding, Ltd. v. Westway Indus., Inc., 4 N.Y.3d 211 (2005)

In Quantum Corporate Funding, a subcontractor sold its accounts receivable to an assignee.  When the general contractor failed to pay its debts, the assignee, or factor, brought suit against the surety for the State Finance Law § 137 payment bonds that the general contractor had been required to purchase.  The surety refused payment and the factor brought suit.  Though the statute is silent on who may sue on the bond, the Court of Appeals ruled that State Finance Law § 137 allows subcontractors’ assignees to recover payment from bond sureties.

Contractors Must Follow Contractual Notice Procedures

Absher Constr. Co. v. Kent Sch. Dist., 77 Wash. App. 137, 890 P.2d 1071 (1995)

In this case, a contractor and subcontractors brought action against a school district for breach of public contract for the construction of an elementary school.  Subcontractor Emerald was hired to work on the school’s HVAC system for Chapman, to whom Absher had subcontracted mechanical work on the project.  Absher’s contract with the school district required all claims to be filed in writing with the district within 14 days of events giving rise to these claims.  Absher did not provide notice of Emerald’s claims until months after Emerald had completed all of its work.  The Superior Court, King County, entered summary judgment for the school district.  The contractor and subcontractors appealed. Continue Reading...

No-Damages-for-Delay Clauses Enforceable Despite Public Entity's Error of Judgment, Lack of Effort or Lack of Complete Diligence

Capital Safety, Inc. v. State, 848 A.2d 863, 369 N.J. Super. 295 (N.J. Super. App. Div. 2004)

In this case, an asbestos removal contractor brought suit against the state for delay damages due to delays cause by the state’s inability to relocate workers to permit asbestos removal.  The court, in this matter, enforced the contract’s no-damages-for-delay clause, finding that such clauses are enforceable even if the delay is the result of the public entity’s “error of judgment, lack of effort, or lack of complete diligence.”
 

Economic Loss Rule Does Not Bar Tort Recovery If Tort Claim is Based on Duty that Exists Independent of Parties' Contract

Robinson Helicopter Co., Inc. v. Dana Corp., 34 Cal. 4th 979 (2004)

In this case, helicopter manufacturer Robinson Helicopter Co., Inc. sued parts supplier Dana Corporation after Dana delivered nonconforming parts to Robinson.  Dana had contracted to supply Robinson with clutches for Robinson’s helicopters.  Dana provided the parts according to Robinson’s specifications for roughly twelve years, but then changed its manufacturing process without notifying Robinson.  For the next sixteen months, Dana delivered nonconforming parts which failed at a much higher rate than the conforming parts.  Robinson notified Dana of the higher failure rate and Dana subsequently switched to a conforming manufacturing process.  Although there were no accidents that lead to physical injury or property damage, Robinson was required to recall and replace the defective parts. 

Robinson sued Dana and the trial awarded Robinson $1.5 million in compensatory damages and $6 million in punitive damages, based on Dana’s knowing misrepresentation or concealment of material facts with the intent to defraud.  Dana appealed.  The court of appeals affirmed the award of compensatory damages but reversed the award of punitive damages, finding that Robinson could not recover in tort when it had only suffered economic loss.

Continue Reading...

Upon Owner's Termination-for-Convenience, Contractor Must Cease All Work and Cancel All Orders

Quality Asphalt Paving, Inc. v. Dept. of Transp. & Public Facilities, 71 P.3d 865 (Alaska 2003)

In this case, a state agency accepted bids on a contract to widen a state highway.  Shortly after the state awarded the contract to a contractor, the state terminated it under a termination-for-convenience clause in the contract.  The contractor sued for costs and damages.  A hearing officer awarded damages to the contractor, but did not award prejudgment interest.  The trial court affirmed, and the parties appealed.

Continue Reading...
Tags:

Subcontractors and Suppliers Must Apply Funds to Specific Project Accounts, Not General Contractor Accounts

Craft v. Stevenson Lumber Yard, Inc., 843 A.2d 1076, 179 N.J. 56 (2004)

In this matter, a project owner filed a complaint demanding the dismissal of a construction lien claim filed by a supplier (Stevenson) after the contractor, who was responsible for paying Stevenson, walked off the job.  The contractor owed Stevenson for multiple past unrelated projects. Therefore, when the contractor provided payments to Stevenson from the plaintiff’s payments, without specifying the project, Stevenson automatically credited the payments to the oldest outstanding invoices, not to those associated with the plaintiff's project.  The supplier subsequently filed a construction lien claim against the real property.  

The court found that the supplier could not arbitrarily assign the payments to different accounts, but rather must apply the contractor’s payments to the individual project account from which payments were derived.  Therefore, the supplier was precluded from filing the lien claim due to its failure to allocate the contractor’s payments to the proper accounts.

Subcontract Pay-If-Paid Provisions Violate New York Public Policy

West-Fair Elec. Contractors v. Aetna Cas. & Sur. Co., 87 N.Y.2d 148 (1995)

In West-Fair, the New York Court of Appeals decided that pay-when-paid provisions in a subcontract, which transfer the risk of an owner’s default from a general contractor to a subcontractor, violate New York public policy as set forth in the Lien Law.  New York’s Lien Law provides that any contractual provision that waives the right to enforce any mechanic’s lien shall be void as against public policy.  The court reasoned that if a subcontractor’s right to be paid could be indefinitely postponed by an owner’s failure to pay the general contractor under a pay-when-paid provision, the subcontractor’s right to enforce its mechanic’s lien would be similarly frustrated and constitute an illegal waiver of lien rights.

Surety Liable for Attorneys Fees and Statutory Penalties Awarded Against Principal

Nat’l Tech. Sys. v. Superior Court, 97 Cal. App. 4th 415 (2002)

In this case, subcontractor National Technical Systems sought to enforce a stop notice release bond against surety United Pacific Insurance Company.  In a prior trial in which UPIC was not joined as a party, NTS had obtained a judgment against a general contractor, including attorneys fees and statutory penalties.  In a subsequent claim against UPIC, NTS had sought to introduce evidence of the judgment and attendant attorneys fees and penalties.  UPIC filed two motions in limine to exclude the evidence.  The first motion sought to exclude evidence of the judgment on the grounds that UPIC was not a party to the prior action and thus not bound by the judgment.  The second motion sought to exclude evidence of the attorneys fees and statutory penalties on the grounds that these awards were not recoverable under the stop notice release bond and that UPIC could only be liable for labor, service and materials furnished on the project.  The trial court granted UPIC’s motions, and NTS sought a writ of mandate directing the court to vacate the order granting the motions.
Continue Reading...

Contractor Cannot Recover Damages for Abandonment or Quantum Meruit from Public Entity

Amelco Elec. v. City of Thousand Oaks, 27 Cal. 4th 228 (2002)

Amelco Electric was granted a prime contract for electric work related to the construction of a civic arts plaza for the City of Thousand Oaks.  During construction, the City issued over a thousand sketches to clarify or change the original contract drawings, of which 248 sketches affected electrical work.  Amelco requested 221 change orders, and the City and Amelco agreed upon 32 change orders.  As a result of the change orders, Amelco received $1 million over the contract price of $6.2 million.  Amelco later submitted additional change orders which were not accepted.  Upon completion of the project, Amelco submitted a $1.7 million claim for costs resulting from the noncaptured costs of the change orders.  By the time of trial, Amelco’s claim had increased to $2.2 million.  The City rejected the claim and Amelco sued for abandonment and breach of contract.  At trial, the jury determined that the City had both breached and abandoned the project and awarded Amelco $2.1 million.  The court of appeals affirmed the award and concluded that, as a matter of law, a public works contract can be abandoned.
Continue Reading...

Statute of Repose Bars Government Enforcement Action

Cyktor v. Aspen Manor Condo. Ass’n, 820 A.2d 129, 359 N.J. Super. 459 (N.J. Super. Ct. App. Div. 2003)

In this case, a condominium developer negotiated an agreement releasing it and its principals from all liability connected with the construction of the development at issue.  The agreement was reached in 1986, several years after construction was completed, and transferred control of the development to the condominium association.  Eleven years later, in 1997, the Department of Community Affairs (DCA) cited the development for certain violations regarding the structure of the facility.  In defense of the citation and the condominium association’s attempts to place liability with the developer, the defendants argued that the action was barred by the statute of repose.  The DCA argued that the statute of repose applied only to claims for damages and did not bar enforcement actions.  The court disagreed with the DCA and held that the statute of repose applies broadly to governmental action.

 

Reasonable Methods for Computing Damages are Actual Total Method and Jury Verdict Method

Power Constructors, Inc. v. Taylor & Hintze, 960 P.2d 20 (Alaska 1998)

In this case, a contractor brought a legal malpractice action against its former law firm and several attorneys.  The contractor’s case was a “trial-within-a-trial” approach, which required the contractor to demonstrate the merits of its underlying case (concerning a deficient powerline construction project) as part of its malpractice case.  At trial, the jury returned a verdict for the contractor, and both parties appealed the damages award in the jury’s verdict.

Continue Reading...
Tags:

Disfavored Total Cost Method of Calculating Damages May Be Used Only in Limited Circumstances

Geolar, Inc. v. Gilbert/Commw. Inc. of Mich., 874 P.2d 937 (Alaska 1994)

In this case, a contractor sued an electric company for breach of contract against the company’s agent for tortious interference with contract.  The contractor also sued the electric company for breach of contract, and calculated its damages based on direct costs, lost of efficiency costs, and delay costs.  The trial court dismissed the contractor’s claim for intentional interference with contract, but the breach of contract claim went to trial, where a jury based an award of damages to the contractor on the contractor’s calculation.

Continue Reading...
Tags:

Deductive Changes Should Affect Contract Price Equitably

M.J. Paquet, Inc. v. N.J. Dep’t of Transportation, 794 A.2d 141, 171 N.J. 378 (2002)

In this case, a contractor submitted an unbalanced bid to the New Jersey Department of Transportation (“DOT”) for the rehabilitation of a bridge with the expense of painting over-estimated and other expenses underestimated.  Following the award of the project, OSHA released new paint safety requirements that the contractor claimed significantly raised the price of the project.  DOT decided that the increased price was too much and decided to excise the bridge painting from the contract.  The contractor then filed suit claiming that DOT was not authorized to delete the painting from the contract and alternatively, that DOT could not subtract the entire amount attributed to painting in the initial unbalanced bid from the contract price.  The Supreme Court concluded that while it was appropriate for the DOT to excise the painting component from the contract it was not proper to simply subtract the value of that item from the initial bid.  Rather, the contractor must have an equitable adjustment to the contract price.
 

Economic Loss Rule Bars Recovery for Construction Defects that do not Cause Property Damage

Aas v. Superior Court, 24 Cal. 4th 627 (2000)

In this case, a condominium homeowners association and condominium owner sued the developer, general contractor and subcontractors who participated in the construction of the condominiums.  The plaintiffs alleged a variety of construction defects related to nearly all components and aspects of the construction, and sought repair costs and damages for diminution in value of their residences.  The defendants sought a motion in limine to exclude evidence relating to alleged construction defects that did not cause property damage.  The trial court granted the defendants’ motions as to the plaintiffs’ tort claims, and the court of appeal denied the plaintiffs’ subsequent petition for a writ of mandate.
Continue Reading...

Functional Equivalent of Privity is Required in Negligent Misrepresentation Cases that Produce Only Economic Injury

Ossining Union Free Sch. Dist. v. Anderson LaRocca Anderson, 73 N.Y.2d 417 (1989)

In Ossining, the Court of Appeals expanded on the holding in Credit Alliance and ruled that a school district, which contracted with an architect, could sue engineers hired by the architect for damages suffered as a result of the engineers’ negligence and malpractice.  The issue addressed by the court was whether privity of contract is required in a negligent misrepresentation case that produces only economic injury.  The court held that a cause of action for negligent misrepresentation which produces only economic injury requires that the underlying relationship between the parties be one of contract or the bond between them so close as to be the “functional equivalent of contractual privity.”  The court laid out a three-prong test following the guidance of Credit Alliance:  (i) that the design professional be aware that its reports are to be used for a particular purpose; (ii) that a known person rely on the reports in furtherance of that purpose; and (iii) that there be some conduct by the design professional linking it to the reliant person and evidencing its understanding of the reliance.

Use of Total Cost Method of Calculating Damages Fails to Prove Cause of Damages

Conom Alaska v. Bell Lavalin, Inc., 842 P.2d 148 (Alaska 1992)

In this case, when a dispute arose regarding the schedule for completing construction, the subcontractor sued the general contractor for professional negligence and breach of contract.  The trial court granted the contractor’s motion to dismiss the professional negligence claim because the subcontractor failed to adequately establish a basis for the jury to determine the amount of damages.  The subcontractor appealed.

Continue Reading...
Tags:

"No Damage for Delay" Clause Does Not Preclude Delay Damages Caused Solely by Owner's Failure to Disclose Material Information Related to Potential Delays

Howard Contracting, Inc. v. G.A. MacDonald Constr. Co., 71 Cal. App. 4th 38 (1999)

This case arose out of a public works contract relating to a construction project to rehabilitate the Venice Canals located in Los Angeles.  The project was owned and designed by the City of Los Angeles, which awarded the general contract to G.A. MacDonald Construction Co., Inc.  The contract between the City and MacDonald contained a limited “no damage for delay” clause, which stated that a contractor was entitled to an extension of time to complete work delayed by unforeseen events but was not entitled to collect damages attributable to the delay.  The contract did provide an exception, however, which specifically provided for payment for unreasonable and unanticipated delays caused by the City.  MacDonald subcontracted portions of the work to Howard Contracting and Soil Retention Systems (“SRS”). Continue Reading...

Architect and Interior Designer Liable for Tortious Interference with Contract Where General Contractor was Terminated on Their Recommendation

DiMaria Constr., Inc. v. Interarch, 799 A.2d 555, 351 N.J. Super 558 (N.J. Super. Ct. App. Div. 2001)

In this case, the general architect and interior designer on a construction project recommended that the owner terminate the general contractor.  The owner, on this advice, terminated the contractor who subsequently filed suit against the architect and interior designer for tortious interference with contract.  In analyzing the claims, the court looked at the four elements of the tort of interference with a business relation or contract:  (1) a protected interest; (2) malice in the sense that the defendant interfered without justification; (3) a reasonable likelihood that the interference caused the loss of the prospective gain; and (4) resulting damages.  The court found that the architect and interior designer were liable for tortious interference.  The court also addressed whether they were acting as agents of the owner and therefore escaped liability.  The court found that question to be a factual issue that was implicitly answered in the affirmative in the jury’s finding of liability.
 

Notwithstanding "No Damage for Delay" Clause, Delay Damages May be Recovered in Certain Circumstances

Corinno Civetta Constr. Corp. v. City of New York, 67 N.Y.2d 297 (1986)

In Corinno Civetta, the Court of Appeals reaffirmed that generally, “no damage for delay” clauses, which bar a contractor from recovering damages for delay in the performance of a contract, are valid and enforceable.  However, even with such a clause, damages may be recovered for:  (i) delays caused by the contractee’s bad faith or willful, malicious, or grossly negligent conduct; (ii) uncontemplated delays; (iii) delays so unreasonable that they constitute an intentional abandonment of the contract by the contractee; and (iv) delays resulting from the contractee’s breach of a fundamental obligation of the contract.

Professionals Can Be Liable to Non-Contracting Parties if Their Relationship Approximates Privity

Credit Alliance Corp. v. Arthur Andersen & Co., 65 N.Y.2d 536 (1985)

In Credit Alliance, the Court of Appeals held that accountants could be liable to noncontractual parties if the relationship of the parties approached that of privity.  Specifically, the court held that an accountant could be liable, absent privity of contract, to a party who relies to his detriment on a negligently prepared financial report if (i) the accountant was aware that the financial reports were to be used for a particular purpose, (ii) in the furtherance of which a known party was intended to rely, and (iii) there must have been some conduct on the part of the accountant linking him to that party which evinces his understanding of that parties’ reliance.

"No Damage for Delay" Clauses Are Generally Valid and Enforceable, with Certain Limited Exceptions

Kalisch-Jarcho, Inc. v. City of New York, 58 N.Y.2d 377 (1983)

In Kalisch-Jarcho, the city entered into a contract with a contractor for the construction of a ventilation system in police headquarters.  The contract contained an exculpatory clause, by which the contractor agreed to make no claims for delay damages occasioned by any act or omission by the city.  After trial on the scope and validity of the delay damages clause, the Court of Appeals ruled that clauses barring a contractor from recovering damages for delay in the performance of a contract are valid, but they will not prevent the recovery of damages resulting from the contractee’s grossly negligent or willful conduct which “smacks of intentional wrongdoing.”

"Pay if Paid" Clauses Are Void and Unenforceable as Against Public Policy Because They Interfere with Subcontractor's Constitutional Right to Assert Mechanic's Lien

Wm. R. Clarke Corp. v. Safeco Ins. Co., 15 Cal. 4th 882 (1997)

In this case, general contractor Keller Construction Company was hired to perform work on a commercial building.  Keller entered into subcontracts with various subcontractors, including Wm. R. Clarke Corporation, and each subcontract contained a “pay if paid” provision.  An addendum to each subcontract stated that the “pay if paid” limitation did not waive the subcontractor’s lien rights and provided that each subcontractor’s mechanic’s lien rights were to be the subcontractor’s sole remedy in the event that the owner failed to pay Keller.  Pursuant to the terms of the prime contract, Keller obtained a payment bond from Safeco Insurance Company that was intended to protect the owner from mechanic’s lien claims brought by any subcontractor.  The bond terms stated that, if Keller failed to pay claims brought by subcontractors, Safeco would assume the obligation to pay.  The building owner became insolvent and stopped making payments to Keller, and Keller declined to pay subcontractors who had recorded mechanic’s liens and filed actions on the payment bond.  The trial court ruled in favor of the subcontractors on the payment bond claim against Safeco.  Safeco appealed, the court of appeals affirmed, and Safeco appealed to the California Supreme Court.
Continue Reading...

Equity May Allow Contractor Who Submits an Incorrect Bid for Public Contract to Rescind Bid Without Forfeiting Bid Bond

Boise Jr. Coll. Dist. v. Mattefs Constr. Co., 92 Idaho 757, 450 P.2d 604 (1969)

Mattefs Construction submitted a bid for the construction of a building for Boise Junior College.  The bid contained a clerical error that omitted one item that constituted 14 percent of the bid.  The court held a contractor is entitled to the equitable relief of rescission if he can establish the following conditions:  “(1) the mistake is material; (2) enforcement of a contract pursuant to the terms on an erroneous bid would be unconscionable; (3) the mistake did not result from violation of a positive legal duty or culpable negligence; (4) the party to whom the bid is submitted will not be prejudiced except by loss of his bargain; and (5) prompt notice of the error is given.”  The court concluded that the clerical error in submitting a bid, which was 14 percent of the total bid, was substantial and material and did not result from culpable negligence.  The court further found that Boise Junior College would not suffer a substantial hardship since Mattefs informed them of the error before they had attempted to accept the offer.  The court did note that not all mistakes entitle a bidder to withdraw his bid, but distinguished this case on the basis that this was a clerical error and not an error in judgment, such as underestimating cost or labor.  Since the court found Mattefs satisfied all five factors, equity required the bid to be withdrawn without forfeiting the bid bond. 

Tags:

Sub-Subcontractor Has No Direct Cause of Action against General Contractor or Landowner

F. Bender, Inc. v. Jos. L. Muscarelle, Inc., 700 A.2d 374, 304 N.J. Super. 282 (N.J. Super. Ct. App. Div. 1997)

In this case, the plaintiff sub-subcontractor sued the general contractor and property owner seeking to recover in quantum meruit for construction work on a parking facility.  The general contractor hired a sub-contractor to perform all of the concrete work who in turn hired the plaintiff.  The sub-contractor was eventually terminated for failure to adequately perform its subcontract agreement with the general contractor.  Plaintiff had no contract with the general contractor or the property owner but sued them for his losses nonetheless.  The court held that where the plaintiff sub-subcontractor had no contractual agreement with the defendants, recovery based upon quantum meruit was precluded.

In so holding, the court pointed out that the plaintiff was not without protection but that he had “failed to protect his rights by filing an appropriate mechanic’s lien” as provided by the Mechanic’s Lien Law.  The court also noted that the result of this opinion did not render the plaintiff helpless to recover but that recovery would properly come from action against the subcontractor.
 

State Agency Entitled to Liquidated Damages Even Though Agency Caused Delay

Southeast Alaska Constr. Co., Inc. v. Dept. of Transp. & Public Facilities, 791 P.2d 339 (Alaska 1990)

This case concerned a public construction project that suffered from design and material deficiencies.  When the contractor failed to complete the project, the agency sued and won on a claim for liquidated damages.  The contractor appealed, arguing that because the agency was responsible for the delay, it should not be entitled to damages.

Continue Reading...
Tags:

Termination Clauses that Provide Profit for Breaching Party Void as Against Public Policy

Saxon Constr. & Mgmt. Co. v. Masterclean of N.C., Inc., 641 A.2d 1056, 273 N.J. Super. 231 (N.J. Super. Ct. App. Div. 2004)

In this case, the court found a termination clause void as against public policy.  The plaintiff, Saxon, a general contractor was awarded a contract to renovate a building owned by the Veterans Administration.  Saxon entered a subcontract with defendant, Masterclean, for asbestos abatement and removal.  Masterclean defaulted and Saxon terminated the contract. The termination clause of the contract provided that if the subcontractor defaulted and the unpaid contract value was less than the expense of finishing the project, then the subcontractor was entitled to the difference.  Saxon was able to procure a substitute contractor at a price lower than Masterclean’s initial contract price.  Masterclean, therefore, invoked the clause to claim the difference between its contract price and the amount paid to the new contractor.  The court found that that type of termination clause violated public policy because it permitted a defaulting party to profit by its breach and discouraged the non-breaching party to minimize its losses.
 

Lost Profits Recoverable as Consequential Damages if Foreseeable

Perini Corp. v. Greate Bay Hotel & Casino, Inc., 610 A.2d 364, 129 N.J. 479 (1992)

In this case, a casino owner sought judicial enforcement of an arbitration award of lost profits against the general contractor hired to manage the casino renovation project.  The project took longer to complete than anticipated and the casino was not fully operational for its peak summer season.  The court held that lost profits may fall under the category of consequential damages and are therefore recoverable as long as they are foreseeable at the time of contract.
 

Withholding Monies Owed on Unrelated Project Constitutes Material Breach

Vinen Corp. v. Alan W. Nau Contracting, Inc., 557 A.2d 1056, 232 N.J. Super. 589 (N.J. Super. Ct. App. Div. 1989)

In this case, the court looked at an action by a contractor against the construction manager for breach of contract for withholding monies from payment that were owed on an unrelated project.  The defendant entered into a contract with the property owner to act as construction manager on a shopping center construction job.  Subsequently, the defendant entered into a subcontract with the plaintiff to act as the site contractor for the project.  During the course of construction, the plaintiff discontinued performance because the defendant withheld $11,000.00 from payment to the plaintiff for monies owed by the plaintiff to the defendant on a different project.  The defendant also insisted that the plaintiff sign a release of lien and threatened that failure to do so would result in defendant’s refusal to pay plaintiff any of the money it was owed for work up to that time.  The plaintiff filed suit for breach and defendant filed a counterclaim.  The court found that the withholding of money constituted a material breach and that the plaintiff was entitled to discontinue performance and was not liable for breach.
 

Subcontractor's Indemnity Clause Must Contain Explicit Waiver of Immunity of Workers' Compensation Act

Brown v. Prime Constr. Co., 102 Wash. 2d 235, 684 P.2d 73 (1984)

In this negligence suit filed by an injured employee of a subcontractor against the general contractor, the latter filed a third-party indemnification claim against the subcontractor.  The case involved the validity of an indemnity provision in a contract between a general contractor and its subcontractor.  The Superior Court, King County, granted summary judgment, and on appeal, the Washington Supreme Court affirmed, holding, among other things, that the subcontractor’s indemnity clause did not clearly and specifically contain a waiver of immunity of the Workers’ Compensation Act.  Therefore, the indemnity clause was not enforceable to compel subcontractor to indemnify general contractor for damages paid to subcontractor’s employee who was injured on the job and sued general contractor for negligence.

State Liable for Damages When Delay Results from State's Failure to Disclose Material Facts

P.T. & L. Constr. Co. v. N.J. Dep’t of Transportation, 531 A.2d 1330, 108 N.J. 539 (1987)

In this case, P.T. & L. Construction Co. was awarded a contract to perform work on a portion of Route 78.  Due to extremely poor working conditions, the project, which was contracted to end on November 15, 1974, was not completed until June of 1976.  P.T. & L. filed suit to recover damages, attributing the delay to the State’s failure to inform them of the actual conditions of the land.  Specifically, where P.T. & L. expected to work in normal or dry conditions, they instead faced wet conditions, including flooding of the work area.  The court, looking at the issue of whether an owner can be liable for damages where it fails to disclose certain critical information regarding the project to bidders, found that a sufficient factual basis existed to warrant recovery for nondisclosure of material facts.
 

Public Contractors Who Follow Plans and Specifications of Another Are Generally Shielded from Liability for Defects by Contract Specifications Defense

Puget Sound Nat’l Bank v. C. B. Lauch Constr. Co., 73 Idaho 68, 245 P.2d 800 (1952)

Saxon Painting entered into a contract with Lauch Construction to do all of the painting for a government housing project.  The contract required Saxon to apply two coats of a certain type of paint, which was provided by Lauch.  Saxon followed the specifications in the contract and completed the painting in a timely manner without any objections to the work from Lauch.  Saxon alleged that he was still owed $19,958 from the contract and three months after completing the work, a lawsuit was commenced.

Continue Reading...
Tags:

California Business and Professions Code § 7031(a) Bars All Claims for Recovery for Unlicensed Contract Work Regardless of Equities

Hydrotech Sys. Ltd. v. Oasis Water Park, 52 Cal. 3d 998 (1991)

Hydrotech Systems Ltd., a New York manufacturer of wave simulation machinery, was hired by a general contractor to build a surfing pool for a California water park.  Hydrotech did not possess a valid California contractor’s license, but the general contractor and Oasis Water Park persuaded Hydrotech to proceed.  The general contractor and Oasis Water Park promised to help arrange for Hydrotech to receive a license and promised to pay for the equipment and services provided by Hydrotech regardless of Hydrotech’s license status.  Hydrotech performed the work without securing a California license.  A payment dispute arose and Hydrotech sued.
Continue Reading...

General Contractor's Recovery for Invalidation of Contract Limited if Contractor Was on Notice of Statutory or Regulatory Violation

Earthmovers of Fairbanks, Inc. v. Dept. of Transp. & Public Facilities, 765 P.2d 1360 (Alaska 1989)

In this case, the Supreme Court of Alaska considered as a case of first impression what remedy is appropriate for a contractor who is awarded a public contract that turns out to violate a statute or regulation.  The facts concerned Earthmovers of Fairbanks (EM), the apparent low bidder for a public project.  When a discrepancy was discovered in the second lowest bid and corrected as permitted by the applicable Standard Specification, the state agency awarded the project to the second lowest bidder.  EM sued and won a permanent injunction.  EM also prevailed on appeal, and the contract was awarded to EM on April 27.  However, on April 30, the Supreme Court of Alaska reversed itself and on May 1, it entered a stay.  Subsequently, EM sued the state agency for damages. 

Continue Reading...
Tags:

No-Damages-for-Delay Clause Precludes Recovery of Delay Damages

Edwin J. Dobson, Inc. v. State, 526 A.2d 1150, 218 N.J. Super. 123 (N.J. Super. App. Div. 1987)

In this case, a contractor brought suit against the state for delay damages arising out of the construction of a public project.  The delays were caused by a variety of reasons primarily stemming from the state’s requirement that the contractor use a specific manufacturer for supplies.  The contract included a “no damage for delay” clause which provided an extension of time for completion, but no additional payment, for damages, in the event of any hindrance or delay in the progress of the work, even if caused by the state.  The court found that the clause was legal and that it precludeed recovery by the plaintiff.

Express Agreement to One-Year Claims Limitation Clause is Enforceable

A.J. Tenwood v. Orange Senior Citizens Hous. Co., 491 A.2d 1280, 200 N.J. Super. 515 (N.J. Super. Ct. App. Div. 1985)

In this case, a construction contractor brought a claim for breach of contract against the owner of a housing project.  The contract between the parties included a one-year claims limitation clause.  The court upheld that one-year limitation relying on precedent that the statutory limitation on contract actions could be waived by the express agreement of both parties.  Therefore, as long as the period is reasonable and does not violate public policy, shortened statutes of limitation clauses are valid.
 

"Pay When Paid" Provision Cannot Indefinitely Delay Payment to Subcontractor

Seal Tite Corp. v. Ehret, Inc., 589 F. Supp. 701 (D.N.J. 1984)

In this case, a subcontractor sued the general contractor for failure to pay in a timely fashion, and moved for summary judgment.  Relying on the “pay when paid” provision of the subcontract, the general contractor claimed that it had not yet been paid in entirety by the owner and therefore the lack of payment to the subcontract was not in breach of the contract.  The court ruled that the “pay when paid” clause was designed to postpone payment by general contractor to subcontractor for a reasonable period after work has been completed to afford the general contractor the opportunity to procure from the owner the funds necessary to pay the subcontractor.  The purpose is not to require the subcontractor to wait to be paid for an indefinite period of time.  Accordingly, the court granted the subcontractor's motion for summary judgment and awarded the amount due under the subcontract.

Multi-Prime Contractors Have Right of Action Against Each Other If Made Third-Party Beneficiaries

Broadway Maint. Corp. v. Rutgers Univ., 447 A.2d 906, 90 N.J. 253 (1982)

In this case, two prime contractors brought suit against the university for damages caused by delays in construction.  In the appeal, the Supreme Court of New Jersey looked at three issues:  (1) whether in an instance of multi-prime contractors each prime contract is liable to the other; (2) whether the owner has a duty to coordinate multi-prime contractors; and (3) whether the exculpatory clause in the prime contracts shielded Rutgers from liability.

The court found that each of the prime contractors, absent privity, had a right of action against the other as long as the contract between the owner and each prime contractor made the remaining contractors third-party beneficiaries.  Second, the court found that an owner entering into multiple prime contracts has the obligation to act in good faith to coordinate the various contractors to avoid unreasonable delay, if the owner has not delegated that responsibility to one of the prime contractors.  Finally, the court found that the exculpatory clause shielded Rutgers from all delays, not just reasonable delays.

Damages Awarded to Plaintiff Stopped from Completing Contract; Calculation Based on the Fair Price of the Entire Work and Lost Profits for Work Not Performed

Zulla Steel v. A & M Gregos, Inc., 415 A.2d 1183, 174 N.J. Super. 124 (N.J. Super. Ct. App. Div. 1980)

In this case, a subcontractor brought an action against the prime contractor for breach after contractor failed to make progress payments when due.  The plaintiff did not complete the project. The court found that the contractor’s failure to make timely payments constituted a material breach and that the plaintiff was therefore justified in terminating its performance.  The court held that the measure of damages in a matter where the plaintiff was stopped from completing the contract is “such a proportion of the entire price as the fair cost of that work bears to the fair cost of the whole work and, in respect to the work not performed, such profits as he would have realized as a result of the complete performance.”  Accordingly, the judgment of the trial court was affirmed, with slight modification.
 

Lack of Privity Does Not Bar Action Against Design Professional for Personal Injury

Conforti & Eisele, Inc. v. John C. Morris Assocs., 418 A.2d 1290, 175 N.J. Super. 341 (N.J Super. Ct. Law Div. 1980)

In this case, a general contractor sued the State and its design professionals for economic damage due to the faulty plans prepared by the design professionals and provided by the State.  There was no privity between the general contractor and the design professional defendants.  However, the court found that a design professional can be held responsible for the losses suffered by a contractor regardless of privity.  The decision was based on a line of New Jersey cases that look with disfavor on the privity doctrine especially with regard to design negligence and physical injuries sustained by third-parties.  The court created a test to determine whether liability should be imposed on design professionals when third-parties are injured.  The elements are:  (1) the extent to which the transaction was intended to affect the plaintiff; (2) the foreseeability of harm to him or her; (3) the degree of certainty that the plaintiff suffered injury; (4) the closeness of the connection between the defendant’s conduct and the injuries suffered; (5) the moral blame attached to the defendant’s conduct; and (6) the policy of preventing future harm.
 

Excessive Changes to Contract Can Justify Abandonment Claim Even if Contract is Completed; Abandonment Damages May Be Calculated According to Total Cost

C. Norman Peterson Co. v. Container Corp. of Am., 172 Cal. App. 3d 628 (1985)

In this case, Container Corporation of America appealed from a trial court judgment in favor of contractor C. Norman Peterson Company (“CNP”).  CCA had hired CNP to perform work to modernize a paper mill.  During the performance of the contract, numerous errors and changes to plan resulted in significant delays and extra costs.  CNP sued for the extra costs associated with the project, claiming the extra costs were caused by CCA’s excessive changes to the plan.  CCA argued that both parties were aware at the time the contract was formed that the plan would require significant revisions.  The trial court found for CNP, holding that CCA’s excessive changes after the project was commenced constituted breach of contract and abandonment.  CNP was allowed to recover its total costs expended and lost profit. CCA appealed.
Continue Reading...

Installation of Air Conditioning Unit Not an "Improvement" within the Context of Statute of Limitations

Rolnick v. Gilson & Sons, Inc., 617 A.2d 288, 260 N.J. Super. 564 (N.J. Super. Ct. App. Div. 1992)

This case concerned a property that was severely damaged by a fire allegedly caused by a defective fan component in the air conditioning system.  The trial court applied the statute of limitations that bars claims over ten years after improvement, finding that the installation of an air conditioning system was an "improvement" within the meaning of the statute.  The appellate court reversed, finding that a mass produced and marketed attic ventilation fan was not an “improvement” within the meaning of the statute and thus the action was not barred.
 

Liquidated Damages Clause in Prime Contract is Incorporated in Subcontract when Subcontract Contains Conduit Clause

Indus. Indem. Co. v. Wick Constr. Co., 680 P.2d 1100 (Alaska 1984)

In this case, the Alaska State Housing Authority (ASHA) awarded a contract for the construction of a courthouse and office building to a general contractor.  The prime contract featured a liquidated damages clause limiting the contractor’s liability to $400 per day of delay.  The subcontract between the general contractor and subcontractor included a so-called “flow down” or “conduit clause” incorporating the liquidated damages clause from the prime contract.  When the general contractor sued the subcontractor for delays, the trial court awarded the general contractor $765,654.00 in total damages.  The subcontractor appealed, arguing that the liquidated damages clause applied.

Continue Reading...
Tags:

Increased Costs Due to Inaccuracy of Contract Drawings Are Recoverable

Golomore Assoc. v. N.J. State Highway Auth., 413 A.2d 361, 173 N.J. Super. 55 (N.J. Super. Ct. App. Div. 1980)

In this case, the court evaluated a claim by a contractor and subcontractor against the State for additional costs of construction. Plaintiffs claimed that the increased costs were due to faulty evaluations of ground elevation provided by the State prior to bidding. The bid submitted to the State was calculated using those faulty measurements and therefore did not adequately predict actual expenses. The court ruled in favor of the plaintiffs, finding that the elevations provided by the State constituted positive averments. Therefore, when the elevation data was shown to be incorrect, contractors were entitled to recover for additional costs.
 

Owner Who Accepts and Takes Possession of Incomplete or Obviously Defective Building Waives Patent and Obvious Defects, but Does Not Waive Latent Defects

Steltz v. Armory, 15 Idaho 551, 99 P. 98 (1908)

Steltz contracted with Armory for the construction of a building in the city of Genesee.  The building was erected and Armory moved in and continued to use it for six weeks, until a windstorm blew down the front of the building.  Armory then refused to pay Steltz arguing that the building was not constructed in a workmanlike manner and Steltz filed this action to recover payment due under the contract.  During trial, evidence was presented that showed the front wall blew down because it had not been properly tied into the rest of the building.  The court held that the defect of not tying the front wall into the building was not an obvious or patent defect, but was a latent defect.  The Court reasoned that if the defect were obvious or patent, then Armory would have accepted the defect by taking possession without conditionally doing so.  The court affirmed the lower court’s decision to offset the cost to repair the defect from the amount still owed under the contract.

Tags:

Court Grants Contractors Damages for Delays Caused by State, Denies Liquidated Damages where State Unable to Establish Extent of Fault of Contractors

Buckley & Co. v. State, 356 A.2d 56, 140 N.J. Super. 289 (N.J. Super. Ct. Law Div. 1975)

In this case, the court adjudicated a claim by two construction companies against the State regarding the construction of Route 78.  The project, namely the creation of a section of the road that involved various bridge constructions as well as electrical, drainage and related work, was finished 87 days later than was provided in the contract and various change orders and 564 days later than the original completion date.  Consequently, the contractors filed suit for delay damages which included various overhead expenses and wages for employees.  The contractors also sought the return of monies withheld by the Department of Transportation as “liquidated damages” for the delay.  The State contended that the delays were the contractors’ fault, that the reasons for the delays given by the contractors did not occur, and that claims for costs were barred by no-damages clauses included in the contract.  The court, concluding that some of plaintiff’s losses were the result of breach by the State, allowed recovery for those losses accordingly.  The court declined to allow the State to withhold liquidated damages where the delay could be attributed actions and inaction by both parties as well as circumstances beyond either party’s control.  The court also held that the construction company had standing to assert claims on behalf of subcontractors.
 

Court Recognizes Implied Warranty of Habitability / Workmanlike Construction in Certain Residential Construction

Hartley v. Ballou, 286 N.C. 51, 209 S.E.2d 776 (1974)

The plaintiff purchased a house from the defendants which one of the defendants had built.  Shortly after the purchase, the plaintiff experienced flooding in the basement of the house.  The plaintiff sued the defendants for breach of express and implied warranties.  Following trial, the trial court entered a judgment in favor of the plaintiff against the builder defendant.  On appeal, the North Carolina Supreme Court recognized an implied warranty of habitability and workmanlike construction by the builder-vendor of a residence to the initial vendee.  The Supreme Court ultimately reduced the damages awarded since it found that they exceeded the builder’s liability under the implied warranty.

Continue Reading...

"Completed and Accepted" Rule Does Not Excuse Architect, General Contractor and Heating Contractor from Liability

Totten v. Gruzen, 245 A.2d 1, 52 N.J. 202 (1968)

In this case, the Supreme Court of New Jersey held that the “completed and accepted” rule does not render defendants immune from liability for injuries sustained from a faulty heating system.  A child resident of a multi-family housing project sustained serious burns from contact with exposed, hot piping that was part of the radiator heating system in the child’s bedroom.  The court found that the lack of privity between the plaintiffs and the defendants was insufficient to excuse the defendants from liability.
 

Lack of Written Document Does Not Preclude Contractor from Recovering in Quantum Meruit for Changes to Initial Plans

Home Owners Const. Co. v. Borough of Glen Rock, 169 A.2d 129, 34 N.J. 305 (1961)

In this case, the court looked at whether a contractor could recover in quantum meruit for services and materials actually provided, even though the work was not authorized in writing.  During the course of construction, the Borough requested the contractor to perform certain extra services and provide additional materials.  Upon the Borough’s refusal to pay these additional expenses, the contractor sought to recover in quantum meruit.  The court found that the lack of writing authorizing these changes did not preclude the contractor from recovery.
 

Factor May be Liable for Diversion of Lien Law Trust Funds

Caristo Constr. Corp. v. Diners Fin. Corp., 21 N.Y.2d 507 (1968)

In Caristo Constr. Corp., a general contractor paid a subcontractor who then turned the money over to a factoring corporation.  The factor failed to file assignment of accounts or a “Notice of Lending” and failed to deposit the general contractor’s checks in depository in trust.  In so doing, the factor participated in diversion of statutory trust funds, despite having returned to the subcontractor simultaneously with the payments “advances” equal to the payments.  The general contractor, who was forced to make payment after the subcontractor became insolvent, prevailed in a suit as subrogee against the factor.

Waiver of Lien Rights Requires Clear, Certain and Unequivocal Evidence

Boise Cascade Corp. v. Distinctive Homes, Inc., 67 Wash. 2d 289, 407 P.2d 452 (1965)

This case involves actions to foreclose on materialmen’s liens by Boise for materials supplied to Distinctive, a building company owned by the landowners, for the construction of two homes.  Distinctive claimed that Boise agreed to waive its lien rights when it accepted two promissory notes.  Boise, however, claimed that the two notes were merely taken as additional security when it agreed to withhold filing the liens if certain timely payments were made. Continue Reading...

Proper Measure of Damages from Defaulting Contractor is Cost of Completion or Necessary Repairs

525 Main St. Corp. v. Eagle Roofing Co., 168 A.2d 33, 34 N.J. 251 (1961)

In this case, the plaintiff property owner, contracted with the defendant for repairs to his roof and a five-year guarantee against leaks with a promise to repair.  During the five years, the defendant disputed the scope of his responsibility and stopped performing repairs.  The trial court found in favor of the plaintiff, concluding that the defendant had breached, but awarded nominal damages.  The plaintiff appealed on the issue of damages.

The defendant argued that the damages should properly be calculated as the difference in value of the entire structure with the defective roof and the value of the building as if the contract had been fully performed.  The court disagreed and found that in the construction context, the cost of repairs or the cost of replacement is the appropriate measure of damages and not a measurement made with reference to the value of the building as whole.